Navarro v. Ordaz Cultured Marble & Onyx, Inc. et al
Plaintiff: |
Rafael Navarro |
Defendant: |
Ordaz Cultured Marble & Onyx, Inc. and Francisco Ordaz |
Case Number: |
3:2013cv00847 |
Filed: |
February 25, 2013 |
Court: |
U.S. District Court for the Northern District of California |
Office: |
San Francisco Office |
County: |
Contra Costa |
Presiding Judge: |
Laurel Beeler |
Nature of Suit: |
Labor: Fair Standards |
Cause of Action: |
29 U.S.C. ยง 201 Denial of Overtime Compensation |
Jury Demanded By: |
Plaintiff |
Available Case Documents
The following documents for this case are available for you to view or download:
Date Filed |
Document Text |
February 23, 2015 |
Filing
71
ORDER APPROVING THE PAGA PENALTY IN THE PARTIES' SETTLEMENT AGREEMENT. Signed by Magistrate Judge Laurel Beeler on 2/23/2015.(lblc2, COURT STAFF) (Filed on 2/23/2015)
|
February 13, 2015 |
Filing
69
ORDER ADMINISTRATIVELY CLOSING THIS ACTION. The Clerk is instructed to administratively close this action. The parties nevertheless shall file a dismissal of this action that complies with the requirements of Federal Rule of Civil Procedure 41(a)(1) by February 27, 2015. Signed by Judge Laurel Beeler on 2/13/2015. (lblc2, COURT STAFF) (Filed on 2/13/2015)
|
July 3, 2014 |
Filing
51
AMENDED ORDER AMENDING THE CASE MANAGEMENT DATES AND DEADLINES. This amended order makes clear that the last day for hearing dispostive motions is now December 18, 2014. Signed by Judge Laurel Beeler on 7/3/2014. (lblc2, COURT STAFF) (Filed on 7/3/2014)
|
June 13, 2014 |
Filing
47
ORDER CONTINUING CMC AND REQUIRING THE PARTIES TO FILE A JOINT CMC STATEMENT BY JUNE 26, 2014. The court CONTINUES the June 19 Further CMC to 11:00 a.m. on July 3, 2014. The court once again ORDERS the parties to file a joint CMC statement that including a chart with new trial deadlines. The parties shall do so by June 26, 2014. Case Management Statement due by 6/26/2014. Further Case Management Conference set for 7/3/2014 11:00 AM in Courtroom C, 15th Floor, San Francisco. Signed by Judge Laurel Beeler on 6/13/2014. (lblc2, COURT STAFF) (Filed on 6/13/2014)
|
October 31, 2013 |
Filing
38
CASE MANAGEMENT AND SCHEDULING ORDER. Signed by Magistrate Judge Laurel Beeler on 10/31/2013. (ls, COURT STAFF) (Filed on 10/31/2013)
|
October 16, 2013 |
Filing
35
ORDER: Re 34 Notice of Substitution of Counsel filed by Ordaz Cultured Marble & Onyx, Inc. Signed by Magistrate Judge Laurel Beeler on 10/16/2013. (ls, COURT STAFF) (Filed on 10/16/2013)
|
July 19, 2013 |
Filing
24
ORDER GRANTING 16 Plaintiff's Motion for Leave to File a First Amended Complaint. Plaintiff shall file a First Amended Complaint as a separate docket entry on ECF within 7 days from the date of this order. Signed by Magistrate Judge Laurel Beeler on 7/19/2013.(lblc2, COURT STAFF) (Filed on 7/19/2013)
|
July 12, 2013 |
Filing
19
AMENDED Case Management and Pretrial Order (Jury). The court issues this amended order only to make clear that the non-expert discovery completion date and the date that expert disclosures are required by the Federal Rules of Civil Procedure is December 19, 2013, not 2014 as the original order (ECF No. 14 ) stated. Signed by Magistrate Judge Laurel Beeler on 7/12/2013. (lblc2, COURT STAFF) (Filed on 7/12/2013)
|
Access additional case information on PACER
Use the links below to access additional information about this case on the U.S. Court's PACER system.
A subscription to PACER is required.
Access this case on the California Northern District Court's Electronic Court Filings (ECF) System
Disclaimer: Justia Dockets & Filings provides public litigation records from the federal appellate and district courts. These filings and docket sheets should not be considered findings of fact or liability, nor do they necessarily reflect the view of Justia.
Why Is My Information Online?