HDB Construction, Inc. v. FEDCON Joint Venture et al
United States of America for the use and benefit of HDB Construction, Inc. and HDB Construction, Inc. |
Western Surety Company and FEDCON Joint Venture |
2:2018cv08843 |
September 21, 2018 |
US District Court for the Eastern District of Louisiana |
Nannette Jolivette Brown |
Dana Douglas |
Martin LC Feldman |
Daniel E Knowles |
Miller Act |
40 U.S.C. § 3131 Miller Act |
None |
Docket Report
This docket was last retrieved on July 12, 2022. A more recent docket listing may be available from PACER.
Document Text |
---|
![]() |
![]() |
![]() |
Filing 14 EXPARTE/CONSENT MOTION to Reopen Case and for Status Conference by HDB Construction, Inc.. (Attachments: #1 Proposed Order, #2 Proposed Order)(Napolitano, Catherine) |
![]() |
Filing 12 Correction of Docket Entry by Clerk re #11 Joint MOTION to Stay . **Filing attorney did not enter HDB Construction, Inc. as additional filer in the blank text box on the docket text screen. Clerk added filer. No further action necessary.** (jeg) |
Filing 11 EXPARTE/CONSENT Joint MOTION to Stay by FEDCON Joint Venture, Western Surety Company, and HDB Construction, Inc. (Attachments: #1 Proposed Order)(Leith, Arthur) Modified filers on 11/7/2018 (jeg). |
![]() |
Filing 9 EXPARTE/CONSENT MOTION for Extension of Time to Answer re #1 Complaint, by FEDCON Joint Venture, Western Surety Company. (Attachments: #1 Proposed Order)Attorney Arthur H. Leith added to party FEDCON Joint Venture(pty:dft), Attorney Arthur H. Leith added to party Western Surety Company(pty:dft).(Leith, Arthur) |
Filing 8 SUMMONS Returned Executed; Western Surety Company served on 9/25/2018, answer due 10/16/2018. (Pelleteri, Maura) Modified text on 9/28/2018 (jeg). |
Filing 7 SUMMONS Returned Executed; FEDCON Joint Venture served on 9/25/2018, answer due 10/16/2018. (Pelleteri, Maura) Modified text on 9/28/2018 (jeg). |
Filing 6 **DEFICIENT** SUMMONS Returned Executed; Western Surety Company served on 9/25/2018, answer due 10/16/2018. (Pelleteri, Maura) Modified on 9/27/2018 (clc). |
Filing 5 **DEFICIENT** SUMMONS Returned Executed; FEDCON Joint Venture served on 9/25/2018, answer due 10/16/2018. (Pelleteri, Maura) Modified on 9/27/2018 (clc). |
Filing 4 Statement of Corporate Disclosure by HDB Construction, Inc. (Pelleteri, Maura) |
Filing 3 Summons Issued as to FEDCON Joint Venture, Western Surety Company. (Attachments: #1 Summons)(sbs) |
Filing 2 Initial Case Assignment to Judge Martin L.C. Feldman and Magistrate Judge Daniel E. Knowles, III. (ess) |
Filing 1 COMPLAINT against All Defendants (Filing fee $400 receipt number 053L-7129332) filed by HDB Construction, Inc. (Attachments: #1 Civil Cover Sheet, #2 Summons, #3 Summons) Attorney Maura Zivalich Pelleteri added to party HDB Construction, Inc.(pty:pla).(Pelleteri, Maura) Modified text on 9/24/2018 (sbs). |
Access additional case information on PACER
Use the links below to access additional information about this case on the US Court's PACER system. A subscription to PACER is required.
Access this case on the Louisiana Eastern District Court's Electronic Court Filings (ECF) System
- Search for Party Aliases
- Associated Cases
- Attorneys
- Case File Location
- Case Summary
- Docket Report
- History/Documents
- Parties
- Related Transactions
- Check Status
Disclaimer: Justia Dockets & Filings provides public litigation records from the federal appellate and district courts. These filings and docket sheets should not be considered findings of fact or liability, nor do they necessarily reflect the view of Justia.