Century Surety Company v. S and R Development, Inc. et al
Century Surety Company |
CMP Construction, Inc. and S and R Development, Inc. |
3:2018cv00746 |
October 26, 2018 |
US District Court for the Southern District of Mississippi |
F Keith Ball |
Daniel P Jordan |
Insurance |
28 U.S.C. ยง 1332 |
Both |
Docket Report
This docket was last retrieved on December 21, 2018. A more recent docket listing may be available from PACER.
Document Text |
---|
Filing 12 ANSWER to #9 Answer to Complaint, Counterclaim of Defendant S& R Development, Inc. by Century Surety Company.(Box, Bradford) |
Filing 11 ANSWER to #10 Answer to Complaint, Counterclaim of Defendant CMP Construction, Inc. by Century Surety Company.(Box, Bradford) |
Filing 10 ANSWER to #1 Complaint, with Jury Demand , COUNTERCLAIM against Century Surety Company by CMP Construction, Inc..(Thurman, Carson) |
Filing 9 ANSWER to #1 Complaint, with Jury Demand , COUNTERCLAIM against Century Surety Company by S and R Development, Inc..(Thurman, Carson) |
TEXT-ONLY ORDER granting #8 Motion for Extension of Time to Answer CMP Construction, Inc. answer due 12/3/2018; S and R Development, Inc. answer due 12/3/2018. NO FURTHER WRITTEN ORDER TO ISSUE FROM THE COURT. Signed by Magistrate Judge F. Keith Ball on 11/27/18 (RBM) |
Filing 8 Unopposed MOTION for Extension of Time to File Answer by CMP Construction, Inc., S and R Development, Inc. (Thurman, Carson) |
Filing 7 NOTICE of Appearance by Preston O. Lee on behalf of CMP Construction, Inc., S and R Development, Inc. (Lee, Preston) |
Filing 6 NOTICE of Appearance by Carson H. Thurman on behalf of CMP Construction, Inc., S and R Development, Inc. (Thurman, Carson) |
Filing 5 NOTICE of Appearance by John C. McCants, III on behalf of CMP Construction, Inc., S and R Development, Inc. (McCants, John) |
DOCKET ANNOTATION as to #3 and #4 : Entries have been modified to show Summons was served on 10/31/18 re: CMP Construction, Inc. answer due 11/21/2018; and served on 10/30/18 re: S and R Development, Inc. answer due 11/20/2018. (PKM) |
Set/Reset Deadlines: CMP Construction, Inc. answer due 11/21/2018; S and R Development, Inc. answer due 11/20/2018. (PKM) |
Filing 4 SUMMONS Returned Executed by Century Surety Company. CMP Construction, Inc. served on 10/31/2018, answer due 11/21/2018. (Box, Bradford) Modified on 11/7/2018 (PKM). |
Filing 3 SUMMONS Returned Executed by Century Surety Company. S and R Development, Inc. served on 10/30/2018, answer due 11/20/2018. (Box, Bradford) Modified on 11/7/2018 (PKM). |
Filing 2 Summons Issued as to CMP Construction, Inc., S and R Development, Inc.. (MGB) |
Filing 1 COMPLAINT For Declaratory Judgment against CMP Construction, Inc., S and R Development, Inc. ( Filing fee $ 400 receipt number 0538-3842238), filed by Century Surety Company. (Attachments: #1 Exhibit 1- Arbitration Demand, #2 Exhibit 2 - Commercial Lines Policy, #3 Civil Cover Sheet)(MGB) |
Access additional case information on PACER
Use the links below to access additional information about this case on the US Court's PACER system. A subscription to PACER is required.
Access this case on the Mississippi Southern District Court's Electronic Court Filings (ECF) System
- Search for Party Aliases
- Associated Cases
- Attorneys
- Case File Location
- Case Summary
- Docket Report
- History/Documents
- Parties
- Related Transactions
- Check Status
Disclaimer: Justia Dockets & Filings provides public litigation records from the federal appellate and district courts. These filings and docket sheets should not be considered findings of fact or liability, nor do they necessarily reflect the view of Justia.