June 22, 2017 |
Filing
211
ORDER REGARDING REPORT AND RECOMMENDATIONS Accepting and Adopting 199 Report and Recommendation, 109 Report and Recommendation, 204 Report and Recommendation, 200 Report and Recommendation, 83 Report and Recommendation, 110 Report and Recommendation, 201 Report and Recommendation, 198 Report and Recommendation and dismissing case with prejudice. Signed by Chief Judge Gloria M. Navarro on 6/22/2017. (Copies have been distributed pursuant to the NEF - JM)
|
June 20, 2017 |
Filing
209
ORDER that 206 American Asphalt & Grading Company's Motion to Deem Settlement Agreement and Release Executed is GRANTED.RECOMMENDED that all claims against all parties be dismissed with prejudice, each side bearing its costs and attorney fees. Signed by Magistrate Judge Cam Ferenbach on 6/19/17. (Copies have been distributed pursuant to the NEF - MMM)
|
June 18, 2017 |
Filing
208
ORDER Granting 205 Stipulation of Dismissal of D.R. Horton, Inc.'s Third-Party Complaint Against Third-Party Defendant Nevada Landscape Corp. with prejudice. Signed by Chief Judge Gloria M. Navarro on 6/18/2017. (Copies have been distributed pursuant to the NEF - SLD)
|
June 13, 2017 |
Filing
207
ORDER re American Asphalt & Grading Company's 206 Motion to Enforce Settlement. Any response due before noon on 6/15/2017. No reply necessary. Signed by Magistrate Judge Cam Ferenbach on 6/13/2017. (Copies have been distributed pursuant to the NEF - SLD)
|
May 26, 2017 |
Filing
204
ORDER and REPORT AND RECOMMENDATION. IT IS HEREBY ORDERED that 203 Third-Party Defendant Nevada Landscape Corp.'s Motion to Deem Settlement Agreement with Defendant/Third-Party Plaintiff D.R. Horton, Inc. Executed is GRANTED. IT IS RECOM MENDED that all claims against all parties be dismissed with prejudice, each side bearing its costs and attorney fees. ( Objections to R&R due by 6/9/2017.) Signed by Magistrate Judge Cam Ferenbach on 5/26/17. (Copies have been distributed pursuant to the NEF - ADR)
|
March 30, 2017 |
Filing
194
MINUTE ORDER. IT IS HEREBY ORDERED that any opposition to 190 , 192 , 193 Motions due by 4/11/2017. Motion Hearing set for 4/14/2017 01:00 PM in LV Courtroom 3D before Magistrate Judge Cam Ferenbach. Signed by Magistrate Judge Cam Ferenbach on 3/30/17. (Copies have been distributed pursuant to the NEF - ADR)
|
February 2, 2017 |
Filing
188
ORDER Granting 187 Stipulation of Dismissal as to Third-Party Defendant U.S. Home Corp. with prejudice. Signed by Chief Judge Gloria M. Navarro on 2/2/17. (Copies have been distributed pursuant to the NEF - ADR)
|
December 23, 2016 |
Filing
181
ORDER Granting 179 Motion to request an exception to the settlement conference attendance requirements. Signed by Magistrate Judge Cam Ferenbach on 12/23/2016. (Copies have been distributed pursuant to the NEF - AF)
|
December 15, 2016 |
Filing
180
ORDER. IT IS HEREBY ORDERED that any opposition to 179 Third Party Defendant M&M Construction, Inc.'s Motion to Request An Exception to the Settlement Conference Attendance Requirements must be filed on or before 12/22/16. No reply necessary. Signed by Magistrate Judge Cam Ferenbach on 12/15/16. (Copies have been distributed pursuant to the NEF - ADR)
|
November 15, 2016 |
Filing
178
ORDER Granting 174 Stipulation to Dismiss Third-Party Complaint Against Third-Party Defendant M&M Construction, Inc. with prejudice. Signed by Chief Judge Gloria M. Navarro on 11/15/16. (Copies have been distributed pursuant to the NEF - ADR)
|
November 14, 2016 |
Filing
175
ORDER Granting 172 Stipulation of Dismissal as to Defendants U.S. Home Corporation, Lennar Corporation and Lennar Sales Corp. Signed by Chief Judge Gloria M. Navarro on 11/14/16. (Copies have been distributed pursuant to the NEF - ADR)
|
October 17, 2016 |
Filing
162
ORDER Granting 157 Stipulation of Dismissal as to Third-Party Defendant, MSI Landscaping, Inc. Signed by Chief Judge Gloria M. Navarro on 10/17/16. (Copies have been distributed pursuant to the NEF - ADR)
|
September 29, 2016 |
Filing
145
ORDER. IT IS HEREBY ORDERED that 137 Third Party Defendant M&M Construction, Inc.'s Motion to Deem Settlement Agreement and Release of Claims Fully Executed is GRANTED. Signed by Magistrate Judge Cam Ferenbach on 9/29/16. (Copies have been distributed pursuant to the NEF - ADR)
|
September 27, 2016 |
Filing
144
ORDER Granting 142 Stipulation to Extend Deadlines re 135 MOTION for Partial Summary Judgment.( Responses due by 9/30/2016.) Signed by Chief Judge Gloria M. Navarro on 9/27/16. (Copies have been distributed pursuant to the NEF - ADR)
|
September 23, 2016 |
Filing
143
ORDER. IT IS HEREBY ORDERED that 129 Third Party Defendant's Motion to Place Settlement on the Record and for Determination of Good Faith Settlement, 129 Motion to Deem Settlement Agreement and Release of Claims Fully Executed by M S Concrete, Co., Inc. are GRANTED. Signed by Magistrate Judge Cam Ferenbach on 9/20/16. (Copies have been distributed pursuant to the NEF - ADR)
|
September 20, 2016 |
Filing
141
ORDER Granting 137 Third-Party Defendant's Motion To Deem Settlement Agreement Executed on an order Shortening Time. Settlement Conference set for 9/29/2016 03:00 PM in LV Courtroom 3D before Magistrate Judge Cam Ferenbach. IT IS FURTHER O RDERED that any opposition to Third Party Defendant's Motion to Deem Settlement Agreement Executed on an Order Shortening Time 137 must be filed on or before 9/26/16. No reply necessary. Signed by Magistrate Judge Cam Ferenbach on 9/20/2016. (Copies have been distributed pursuant to the NEF - DL)
|
August 25, 2016 |
Filing
134
MINUTE ORDER. IT IS HEREBY ORDERED that any opposition 129 to Third-Party Defendant MS Concrete Co., Inc.'s Motion to Place Settlement on the Record and For Determination of Good Faith Settlement on an Order Shortening Time and 133 Thi rd-Party Defendant MS Concrete Co., Inc.'s Motion to Deem Settlement Agreement and Release of Claims Fully Executed by MS Concrete, Co., Inc.'s on an Order Shortening Time must be filed on or before 9/6/16. Motion Hearing set for 9/8/2016 03:00 PM in LV Courtroom 3D before Magistrate Judge Cam Ferenbach. Signed by Magistrate Judge Cam Ferenbach on 8/25/16. (Copies have been distributed pursuant to the NEF - ADR)
|
August 22, 2016 |
Filing
128
ORDER. IT IS HEREBY ORDERED that 114 M&M Construction's Motion for Determination of Good Faith Settlement is GRANTED. IT IS FURTHER ORDERED that 111 D.R. Horton's Motion to Amend Its Third-Party Complaint is GRANTED. Signed by Magistrate Judge Cam Ferenbach on 8/22/16. (Copies have been distributed pursuant to the NEF - ADR)
|
August 3, 2016 |
Filing
123
ORDER. IT IS HEREBY ORDERED that the hearing on 111 Defendant/Third-Party Plaintiff D.R. Horton, Inc.'s Motion for Leave to Amend Third-Party Complaint scheduled for 11:00 a.m., 8/8/16 is RESCHEDULED to 11:00 a.m., 8/12/16, in courtroom 3D. Signed by Magistrate Judge Cam Ferenbach on 8/2/16. (Copies have been distributed pursuant to the NEF - ADR)
|
August 1, 2016 |
Filing
120
ORDER. IT IS HEREBY ORDERED that the hearing on 114 M&M Construction, Inc.'s Motion for Determination of Good Faith Settlement on an Order Shortening Time scheduled for 10:00 a.m., 8/12/16 is RESCHEDULED to 11:00 a.m., 8/12/16, in courtroom 3D. Signed by Magistrate Judge Cam Ferenbach on 8/1/16. (Copies have been distributed pursuant to the NEF - ADR)
|
July 26, 2016 |
Filing
115
ORDER. IT IS HEREBY ORDERED that an opposition to Third-Party Defendant M&M Construction, Inc.'s 114 Motion for Determination of Good Faith Settlement on an Order Shortening Time must be filed on or before August 3, 2016. No reply necessary . IT IS FURTHER ORDERED that a hearing on Third-Party Defendant M&M Construction, Inc.'s 114 Motion for Determination of Good Faith Settlement on an Order Shortening Time is scheduled for 10:00 a.m., August 12, 2016, in courtroom 3D before Magistrate Judge Cam Ferenbach. Signed by Magistrate Judge Cam Ferenbach on 07/26/2016. (Copies have been distributed pursuant to the NEF - NEV)
|
July 21, 2016 |
Filing
113
ORDER re 111 Motion for Leave to Amend Third-Party Complaint. Motion Hearing set for 8/8/2016 11:00 AM in LV Courtroom 3D before Magistrate Judge Cam Ferenbach. Signed by Magistrate Judge Cam Ferenbach on 7/21/16. (Copies have been distributed pursuant to the NEF - ADR)
|
July 20, 2016 |
Filing
112
ORDER that any opposition to Defendant/Third-Party Plaintiff D.R. Horton, Inc.'s Motion for Leave to Amend Third-Party Complaint on Order Shortening Time (ECF No. 111 ) must be filed on or before July 26, 2016. Any reply in support of the motion must be filed on or before August 1, 2016. Signed by Magistrate Judge Cam Ferenbach on 7/20/16. (Copies have been distributed pursuant to the NEF - MMM)
|
July 7, 2016 |
Filing
105
ORDER Granting 103 Stipulation to Dismiss Third-Party Defendant C&H Concrete, LLC without prejudice. C&H Concrete, LLC terminated. Signed by Chief Judge Gloria M. Navarro on 7/7/16. (Copies have been distributed pursuant to the NEF - ADR)
|
June 14, 2016 |
Filing
98
ORDER that a Hearing 96 Motion for Determination of Good Faith Settlement is set for 7/13/2016 at 10:00 AM in LV Courtroom 3D before Magistrate Judge Cam Ferenbach. Signed by Magistrate Judge Cam Ferenbach on 6/13/16. (Copies have been distributed pursuant to the NEF - MMM)
|
June 13, 2016 |
Filing
99
ORDER that the Complaint against third-party defendant New Creation Masonry, Inc. is Dismissed with Prejudice. Signed by Chief Judge Gloria M. Navarro on 6/13/16. (Copies have been distributed pursuant to the NEF - JM)
|
June 10, 2016 |
Filing
97
ORDER Granting 95 Stipulation of Dismissal with prejudice as to Third-Party Defendant Bravo Underground, Inc. Signed by Chief Judge Gloria M. Navarro on 6/10/2016. (Copies have been distributed pursuant to the NEF - SLD)
|
June 8, 2016 |
Filing
94
ORDER re ECF No. 93 Motion for Determination of Good Faith Settlement : Motion Hearing set for 7/13/2016 at 10:00 AM in LV Courtroom 3D before Magistrate Judge Cam Ferenbach. Signed by Magistrate Judge Cam Ferenbach on 6/8/2016. (Copies have been distributed pursuant to the NEF - DRM)
|
April 11, 2016 |
Filing
79
ORDER. IT IS HEREBY ORDERED that a hearing on Third-Party Defendant Bravo Underground, Inc.'s Motion for Determination of Good Faith Settlement on Order Shortening Time 67 is scheduled for 3:00 p.m., 5/3/16, in courtroom 3D. Signed by Magistrate Judge Cam Ferenbach on 4/11/16. (Copies have been distributed pursuant to the NEF - PS)
|
March 22, 2016 |
Filing
76
ORDER Granting 69 Stipulation of Dismissal. IT IS ORDERED that any claims against AA&G by U.S. Home, be dismissed without prejudice. Signed by Chief Judge Gloria M. Navarro on 3/22/16. (Copies have been distributed pursuant to the NEF - PS)
|