Baker Hughes Energy Services LLC et al v. International Engineering & Construction S.A. et al
Pressure Control Systems Nigeria Ltd., Baker Hughes Energy Services LLC, GE International Operations (Nigeria) Ltd., GE Oil & Gas, LLC, GE Oil & Gas, Inc., Baker Hughes Co. and Baker Hughes Holdings LLC |
Greenville Liquified Natural Gas Co., Ltd. and International Engineering & Construction S.A. |
1:2021cv01961 |
March 5, 2021 |
US District Court for the Southern District of New York |
Jesse M Furman |
Other Statutes: Arbitration |
09 U.S.C. § 207 |
None |
Docket Report
This docket was last retrieved on November 17, 2021. A more recent docket listing may be available from PACER.
Document Text |
---|
Filing 21 REPLY MEMORANDUM OF LAW / Sur-Reply Memorandum of Law in Support of the Petition to Vacate Arbitral Award #20 . Document filed by International Engineering & Construction S.A...(Hille, David) |
Filing 20 ORDER granting #19 Letter Motion for Leave to File Document. Application GRANTED, although the Court will consider the arguments in the sur-reply only to the extent that they respond to new arguments advanced in the reply. The Clerk of Court is directed to terminate ECF No. 19. SO ORDERED. (Signed by Judge Jesse M. Furman on 4/22/2021) (rj) |
Filing 19 LETTER MOTION for Leave to File Sur-Reply addressed to Judge Jesse M. Furman from David G. Hille dated April 21, 2021. Document filed by International Engineering & Construction S.A.. (Attachments: #1 Exhibit A).(Hille, David) |
Filing 18 REPLY MEMORANDUM OF LAW in Support of Petition to Confirm Arbitral Award. Document filed by Baker Hughes Co., Baker Hughes Energy Services LLC, Baker Hughes Holdings LLC, GE International Operations (Nigeria) Ltd., GE Oil & Gas, LLC, Pressure Control Systems Nigeria Ltd...(Kiefer, David) |
Filing 17 REPLY MEMORANDUM OF LAW in Support of the Petition to Vacate Arbitral Award and in Opposition to Petition to Confirm Arbitral Award. Document filed by International Engineering & Construction S.A.. (Attachments: #1 Exhibit A, #2 Exhibit B, #3 Exhibit C).(Hille, David) |
Filing 16 DECLARATION of Joshua S. Wan re: #15 Memorandum of Law in Opposition, . Document filed by Baker Hughes Co., Baker Hughes Energy Services LLC, Baker Hughes Holdings LLC, GE International Operations (Nigeria) Ltd., GE Oil & Gas, LLC, Pressure Control Systems Nigeria Ltd.. (Attachments: #1 Exhibit A, #2 Exhibit B, #3 Exhibit C, #4 Exhibit D, #5 Exhibit E, #6 Exhibit F).(Kiefer, David) |
Filing 15 MEMORANDUM OF LAW in Opposition / Petitioners' Memorandum of Law in Support of Petition to Confirm Arbitral Award and in Opposition to Respondents' Petition to Vacate Arbitral Award. Document filed by Baker Hughes Co., Baker Hughes Energy Services LLC, Baker Hughes Holdings LLC, GE International Operations (Nigeria) Ltd., GE Oil & Gas, LLC, Pressure Control Systems Nigeria Ltd...(Kiefer, David) |
Filing 14 NOTICE OF APPEARANCE by Elizabeth Rachel Oger-Gross on behalf of International Engineering & Construction S.A...(Oger-Gross, Elizabeth) |
Filing 13 ORDER granting (12) Letter Motion to Consolidate Cases in case 1:21-cv-01961-JMF; granting (9) Letter Motion to Consolidate Cases in case 1:21-cv-02003-JMF. Application GRANTED as to both requests (consolidation and the parties' proposed briefing schedule and structure). The Clerk of Court is directed to file this endorsement on both above-captioned dockets and to terminate 21-CV-1961, ECF No. 12, and 21-CV-2003, ECF No. 9. The Clerk of Court is further directed to consolidate 21-CV-1961 and 21-CV-2003 under case number 21-CV-1961, and to close 21-CV-2003. All future filings shall be on the 21-CV-1961 docket. SO ORDERED. (Signed by Judge Jesse M. Furman on 3/16/21) Filed In Associated Cases: 1:21-cv-01961-JMF, 1:21-cv-02003-JMF (yv) |
Filing 12 JOINT LETTER MOTION to Consolidate Cases 21cv2003 and 21cv1961 and in response to this Court's Order dated March 12, 2021 addressed to Judge Jesse M. Furman from David M. Kiefer dated 3/15/2021. Document filed by Baker Hughes Energy Services LLC, GE International Operations (Nigeria) Ltd., Greenville Liquified Natural Gas Co., Ltd., International Engineering & Construction S.A., Pressure Control Systems Nigeria Ltd...(Kiefer, David) |
Filing 11 NOTICE OF APPEARANCE by Joshua Douglas Weedman on behalf of International Engineering & Construction S.A...(Weedman, Joshua) |
Filing 10 NOTICE OF APPEARANCE by David Grant Hille on behalf of International Engineering & Construction S.A...(Hille, David) |
Filing 9 ORDER granting #8 CONSENT LETTER MOTION for Extension of Time/Setting Briefing Schedule addressed to Judge Jesse M. Furman from David Kiefer dated 3/12/2021. Document filed by Baker Hughes Energy Services LLC, GE International Operations (Nigeria) Ltd., Greenville Liquified Natural Gas Co., Ltd., International Engineering & Construction S.A., Pressure Control Systems Nigeria Ltd. Application GRANTED for the moment. That said, the Court is inclined to think that it would be better to set a briefing schedule and structure that did not involve two parallel motions with the likelihood of highly duplicative briefing. Counsel shall promptly confer and, no later than March 15, 2021, submit a joint letter indicating whether they believe there is a more efficient briefing structure and schedule or not. The Clerk of Court is directed to file this endorsement on both above-captioned dockets and to terminate 21-CV-1961, ECF No. 8, and 21-CV-2003, ECF No. 5. SO ORDERED. (Signed by Judge Jesse M. Furman on 3/12/2021) (rjm) |
Filing 8 CONSENT LETTER MOTION for Extension of Time /Setting Briefing Schedule addressed to Judge Jesse M. Furman from David Kiefer dated 3/12/2021. Document filed by Baker Hughes Energy Services LLC, GE International Operations (Nigeria) Ltd., Greenville Liquified Natural Gas Co., Ltd., International Engineering & Construction S.A., Pressure Control Systems Nigeria Ltd...(Kiefer, David) |
Set/Reset Deadlines: Responses due by 3/25/2021. Replies due by 4/8/2021. (rjm) |
Filing 7 ORDER re: #1 Petition to Compel/Confirm/Modify/Stay/Vacate Arbitration, filed by Pressure Control Systems Nigeria Ltd., GE International Operations (Nigeria) Ltd., Baker Hughes Energy Services LLC. On March 8, 2021, Petitioners filed a petition to confirm an arbitration award. Proceedings to confirm an arbitration award must be "treated as akin to a motion for summary judgment." D.H. Blair & Co., Inc. v. Gottdiener, 462 F.3d 95, 109 (2d Cir. 2006). Accordingly, it is hereby ORDERED that Petitioners shall file and serve any additional materials with which they intend to support their petition to confirm by March 15, 2021. Respondents' opposition, if any, is due on March 29, 2021. Petitioners reply, if any, is due April 5, 2021. Petitioners shall serve the petition and all supporting papers, as well as this Order, upon Respondents electronically and by overnight mail no later than March 15, 2021, and shall file an affidavit of such service with the court no later than March 16, 2021. SO ORDERED. ( Responses due by 3/29/2021, Replies due by 4/5/2021.) (Signed by Judge Jesse M. Furman on 3/8/2021) (kv) |
Magistrate Judge Sarah Netburn is so designated. Pursuant to 28 U.S.C. Section 636(c) and Fed. R. Civ. P. 73(b)(1) parties are notified that they may consent to proceed before a United States Magistrate Judge. Parties who wish to consent may access the necessary form at the following link: #https://nysd.uscourts.gov/sites/default/files/2018-06/AO-3.pdf. (gp) |
CASE OPENING INITIAL ASSIGNMENT NOTICE: The above-entitled action is assigned to Judge Jesse M. Furman. Please download and review the Individual Practices of the assigned District Judge, located at #https://nysd.uscourts.gov/judges/district-judges. Attorneys are responsible for providing courtesy copies to judges where their Individual Practices require such. Please download and review the ECF Rules and Instructions, located at #https://nysd.uscourts.gov/rules/ecf-related-instructions..(gp) |
Case Designated ECF. (gp) |
Filing 6 RULE 7.1 CORPORATE DISCLOSURE STATEMENT. Identifying Corporate Parent Baker Hughes Company for Pressure Control Systems Nigeria Ltd.; Corporate Parent GENERAL ELECTRIC COMPANY for GE International Operations (Nigeria) Ltd.; Corporate Parent GENERAL ELECTRIC COMPANY, Corporate Parent Baker Hughes Holdings LLC for Baker Hughes Energy Services LLC. Document filed by Baker Hughes Energy Services LLC, GE International Operations (Nigeria) Ltd., Pressure Control Systems Nigeria Ltd...(Kiefer, David) |
Filing 5 CIVIL COVER SHEET filed..(Kiefer, David) |
Filing 4 DECLARATION of Joshua S. Wan in Support re: #1 Petition to Compel/Confirm/Modify/Stay/Vacate Arbitration,. Document filed by Baker Hughes Energy Services LLC, GE International Operations (Nigeria) Ltd., Pressure Control Systems Nigeria Ltd.. (Attachments: #1 Exhibit A- Award, #2 Exhibit B - Respondents' Notice of Demand for and Commencement of Arbitration, dated July 31, 2018, #3 Exhibit C - Petitioners Demand for Arbitration, dated August 14, 2018, which asserted counterclaims against Respondents., #4 Exhibit D - Parties agreement to arbitrate, located in the three contracts between Petitioners and Respondent International Engineering & Construction S.A.).(Kiefer, David) |
Filing 3 MEMORANDUM OF LAW in Support re: #1 Petition to Compel/Confirm/Modify/Stay/Vacate Arbitration, . Document filed by Baker Hughes Energy Services LLC, GE International Operations (Nigeria) Ltd., Pressure Control Systems Nigeria Ltd...(Kiefer, David) |
Filing 2 NOTICE of Petition to Confirm Arbitral Award re: #1 Petition to Compel/Confirm/Modify/Stay/Vacate Arbitration,. Document filed by Baker Hughes Energy Services LLC, GE International Operations (Nigeria) Ltd., Pressure Control Systems Nigeria Ltd...(Kiefer, David) |
Filing 1 PETITION TO CONFIRM ARBITRAL AWARD ARBITRATION. (Filing Fee $ 402.00, Receipt Number ANYSDC-24214383).Document filed by Baker Hughes Energy Services LLC, Pressure Control Systems Nigeria Ltd., GE International Operations (Nigeria) Ltd...(Kiefer, David) |
Access additional case information on PACER
Use the links below to access additional information about this case on the US Court's PACER system. A subscription to PACER is required.
Access this case on the New York Southern District Court's Electronic Court Filings (ECF) System
- Search for Party Aliases
- Associated Cases
- Attorneys
- Case File Location
- Case Summary
- Docket Report
- History/Documents
- Parties
- Related Transactions
- Check Status
Disclaimer: Justia Dockets & Filings provides public litigation records from the federal appellate and district courts. These filings and docket sheets should not be considered findings of fact or liability, nor do they necessarily reflect the view of Justia.