In re River Construction Inc., as Owner and operator of the RC-100 for Exoneration from or Limitation of Liability
Petitioner: River Construction Inc.
Claimant: Russell Marine, LLC
3Rd Party Defendant: Lloyd Engineering, Inc.
Case Number: 4:2022cv02413
Filed: July 20, 2022
Court: US District Court for the Southern District of Texas
Presiding Judge: Andrew S Hanen
Referring Judge: Sam S Sheldon
Nature of Suit: Marine
Cause of Action: 28 U.S.C. § 1333 Admiralty
Jury Demanded By: None
Docket Report

This docket was last retrieved on September 17, 2022. A more recent docket listing may be available from PACER.

Date Filed Document Text
September 17, 2022 Opinion or Order Filing 34 ORDER granting #33 Motion for Extension of Time; Motion-related deadline set re: #33 Unopposed MOTION for Extension of Time Deadline for Filing Joint Case Management Plan. Joint Discovery/Case Management Plan due by 9/26/2022..(Signed by Magistrate Judge Sam S Sheldon) Parties notified.(sjones, 4)
September 17, 2022 CONTINUATION OF ENTRY #34 FOR STATISTICAL PURPOSES.(Signed by Magistrate Judge Sam S Sheldon) Parties notified.(sjones, 4)
September 15, 2022 Filing 33 Unopposed MOTION for Extension of Time Deadline for Filing Joint Case Management PlanMotions referred to Sam S Sheldon. by River Construction Inc., filed. Motion Docket Date 10/6/2022. (Attachments: #1 Proposed Order)(Asprodites, Rowen)
September 14, 2022 Filing 32 Summons Issued as to Lloyd Engineering, Inc.. Issued summons delivered to plaintiff by NEF, filed.(jdav, 4)
September 14, 2022 Summons Not Issued as to Lloyd Engineering, Inc. due to these deficiencies: Party named on summons is not a named counter defendant on the case. Attorney or Plaintiff notified of deficiencies by NEF, filed.(AkeitaMichael, 4)
September 13, 2022 Filing 31 Request for Issuance of Summons as to Lloyd Engineering, Inc., filed.(Asprodites, Rowen)
September 13, 2022 Filing 30 Request for Issuance of Summons as to River Construction Inc., filed.(Asprodites, Rowen)
September 12, 2022 Filing 29 ANSWER to #14 Claim, THIRD PARTY COMPLAINT against Lloyd Engineering, Inc. by River Construction Inc., filed.(Asprodites, Rowen)
September 12, 2022 Filing 28 ANSWER to #24 Claim, COUNTERCLAIM against Russell Marine, LLC by River Construction Inc., filed.(Asprodites, Rowen)
September 9, 2022 Filing 27 RESPONSE in Opposition to #25 MOTION Motion to Dissolve Limitation Injunction and Objection to Claim Filed by BWC Terminals, LLC, filed by River Construction Inc.. (Attachments: #1 Exhibit A, #2 Exhibit B, #3 Exhibit C, #4 Exhibit D, #5 Proposed Order)(Asprodites, Rowen)
September 9, 2022 Filing 26 RESPONSE in Opposition to #25 MOTION Motion to Dissolve Limitation Injunction and Objection to Claim Filed by BWC Terminals, LLC, filed by Contanda Terminals, LLC. (Attachments: #1 Proposed Order Order Denying Russell Marine's Motion and Objection to Claim Filed by Contanda)(Strickland, Timothy)
August 26, 2022 Filing 25 MOTION Motion to Dissolve Limitation Injunction and Objection to Claim Filed by BWC Terminals, LLCMotions referred to Sam S Sheldon. by Russell Marine, LLC, filed. Motion Docket Date 9/16/2022. (Attachments: #1 Exhibit 1, #2 Exhibit 2, #3 Proposed Order Dismissing Injunction, #4 Proposed Order Contanda Claim)(Diamond, Adam)
August 26, 2022 Filing 24 CLAIM filed by Russell Marine, LLC.(Diamond, Adam)
August 26, 2022 Filing 23 ANSWER to #1 Complaint, by Russell Marine, LLC, filed.(Diamond, Adam)
August 17, 2022 Opinion or Order Filing 22 ORDER: (Signed by Magistrate Judge Sam S Sheldon) Parties notified.(sjones, 4)
August 17, 2022 Opinion or Order Filing 21 ORDER: Brief due by 8/26/2022 Responses due by 9/9/2022. Replies due by 9/23/2022(Signed by Magistrate Judge Sam S Sheldon) Parties notified.(sjones, 4)
August 17, 2022 Opinion or Order Filing 20 MINUTE ENTRY ORDER: The Court held a hearing on the Motion to Clarify the Stay (Dkt. No. 7) on August 15, 2022. At the hearing, the parties agreed on a proposed briefing schedule regarding the Stay and also agreed on the protocol for the destructive testing. The Court ORDERED the parties to submit joint proposed Orders regarding the same. Appearances: Aaron Greenbaum, Jan Huber, Brian Zimmerman, Adam Diamond, David James, Ken Woodand, Tim Strickland, Rowen Asphrodites. Ct Reporter: ERO. Digital Number: 3:00-3:33PM.(Signed by Magistrate Judge Sam S Sheldon) Parties notified.(sjones, 4)
August 16, 2022 Filing 19 Joint PROPOSED ORDER re Destructive Examination, filed.(Siahatgar, Bijan)
August 16, 2022 Filing 18 Joint PROPOSED ORDER re Briefing Schedule, filed.(Siahatgar, Bijan)
August 12, 2022 Filing 17 REPLY TO RIVER CONSTRUCTION INC.'S OPPOSITION TO EXPEDITED MOTION TO CLARIFY STAY, filed by Russell Marine, LLC. (Siahatgar, Bijan)
August 12, 2022 Filing 16 PROPOSED ORDER Denying Russell Marine's Expedited Motion to Clarify Stay re: #15 Response in Opposition to Motion, filed.(Strickland, Timothy)
August 12, 2022 Filing 15 RESPONSE in Opposition to #7 MOTION to Expedite Motion to Clarify Stay, filed by Contanda Terminals, LLC. (Strickland, Timothy)
August 12, 2022 Filing 14 CLAIM of BWC Terminals LLC F/K/A Contanda Terminals filed by Contanda Terminals, LLC.(Strickland, Timothy)
August 12, 2022 Filing 13 ANSWER to #1 Complaint, by Contanda Terminals, LLC, filed.(Strickland, Timothy)
August 10, 2022 Filing 12 RESPONSE in Opposition to #7 MOTION to Expedite Motion to Clarify Stay, filed by River Construction Inc.. (Attachments: #1 Exhibit A, #2 Exhibit B, #3 Exhibit C, #4 Exhibit D, #5 Exhibit E, #6 Exhibit F, #7 Exhibit G)(Greenbaum, Aaron)
August 8, 2022 Filing 11 NOTICE of Setting re: #7 MOTION to Expedite Motion to Clarify Stay. Parties notified. Motion Hearing set for 8/15/2022 at 03:00 PM in by video before Magistrate Judge Sam S Sheldon, filed. (sjones, 4)
August 8, 2022 Filing 10 NOTICE of Appearance by Adam R. Diamond on behalf of Russell Marine, LLC, filed. (Diamond, Adam)
August 5, 2022 Filing 9 CORPORATE DISCLOSURE STATEMENT by River Construction Inc., filed.(Greenbaum, Aaron)
August 5, 2022 Filing 8 CERTIFICATE OF INTERESTED PARTIES by River Construction Inc., filed.(Greenbaum, Aaron)
August 4, 2022 Filing 7 MOTION to Expedite Motion to Clarify StayMotions referred to Sam S Sheldon. by Russell Marine, LLC, filed. Motion Docket Date 8/25/2022. (Attachments: #1 Exhibit 1 - 2022.06.23 - Contanda Letter Re Construction, #2 Exhibit 2 - 2022-06.29- Ltr to Strickland, #3 Exhibit 3 - Signed Order on Plaintiffs' Amended Mot Compel, #4 Exhibit 4 - Hearing Transcript, #5 Exhibit 5 - Email between Contanda and Russell Marine, #6 Exhibit 6 - 2022.08.04 - Ltr from River Construction)(Siahatgar, Bijan)
July 29, 2022 Filing 6 NOTICE of Resetting re: #2 Order for Initial Conference - FORM,. Parties notified. Initial Conference reset for 9/29/2022 at 10:10 AM in by video before Magistrate Judge Sam S Sheldon, filed. (JessicaVillarreal, 3)
July 27, 2022 Filing 5 NOTICE TO CLAIMANTS OF COMPLAINT FOREXONERATION FROM OR LIMITATION OF LIABILITY re: #1 Complaint,, filed. (sjones, 4)
July 26, 2022 Opinion or Order Filing 4 ORDER APPROVING PETITIONERS AD INTERIM STIPULATION FOR VALUE AND DIRECTING ISSUANCE OF NOTICE AND RESTRAINING PROSECUTION OF CLAIMS (Signed by Magistrate Judge Sam S Sheldon) Parties notified.(sjones, 4) Modified on 7/26/2022 (sjones, 4).
July 25, 2022 Opinion or Order Filing 3 ORDER OF REFERRAL TO MAGISTRATE JUDGE to Magistrate Magistrate Judge Sam S Sheldon(Signed by Judge Andrew S Hanen) Parties notified.(jdav, 4)
July 21, 2022 Opinion or Order Filing 2 ORDER for Initial Pretrial and Scheduling Conference and Order to Disclose Interested Persons. Initial Conference set for 9/29/2022 at 10:10 AM in Courtroom 700 before Magistrate Judge Sam S Sheldon. (Signed by Judge Andrew S Hanen) Parties notified.(AkeitaMichael, 4)
July 20, 2022 Filing 1 COMPLAINT against River Construction Inc. (Filing fee $ 402 receipt number ATXSDC-28493939) filed by River Construction Inc.. (Attachments: #1 Civil Cover Sheet, #2 Exhibit A, #3 Exhibit B, #4 Exhibit C, #5 Exhibit D, #6 Exhibit E, #7 Exhibit F, #8 Exhibit G, #9 Notice to Claimants, #10 Ad Interim Stipulation for Value / Letter of Undertaking, #11 Verification, #12 Order Approving Petitioner's Ad Interim)(Greenbaum, Aaron)

Access additional case information on PACER

Use the links below to access additional information about this case on the US Court's PACER system. A subscription to PACER is required.

Access this case on the Texas Southern District Court's Electronic Court Filings (ECF) System

Search for this case: In re River Construction Inc., as Owner and operator of the RC-100 for Exoneration from or Limitation of Liability
Search News [ Google News | Marketwatch | Wall Street Journal | Financial Times | New York Times ]
Search Web [ Unicourt | Legal Web | Google | Bing | Yahoo | Ask ]
Petitioner: River Construction Inc.
Represented By: Aaron Benjamin Greenbaum
Search News [ Google News | Marketwatch | Wall Street Journal | Financial Times | New York Times ]
Search Finance [ Google Finance | Yahoo Finance | Hoovers | SEC Edgar Filings ]
Search Web [ Unicourt | Justia Dockets | Legal Web | Google | Bing | Yahoo | Ask ]
Claimant: Russell Marine, LLC
Represented By: Adam Ross Diamond
Represented By: Bijan R Siahatgar
Search News [ Google News | Marketwatch | Wall Street Journal | Financial Times | New York Times ]
Search Finance [ Google Finance | Yahoo Finance | Hoovers | SEC Edgar Filings ]
Search Web [ Unicourt | Justia Dockets | Legal Web | Google | Bing | Yahoo | Ask ]
3rd party defendant: Lloyd Engineering, Inc.
Search News [ Google News | Marketwatch | Wall Street Journal | Financial Times | New York Times ]
Search Finance [ Google Finance | Yahoo Finance | Hoovers | SEC Edgar Filings ]
Search Web [ Unicourt | Justia Dockets | Legal Web | Google | Bing | Yahoo | Ask ]

Disclaimer: Justia Dockets & Filings provides public litigation records from the federal appellate and district courts. These filings and docket sheets should not be considered findings of fact or liability, nor do they necessarily reflect the view of Justia.


Why Is My Information Online?