Fyfe Co., LLC et al v. Structural Group, Inc. et al
Fyfe Co., LLC, Fibrwrap Construction Services USA, Inc. and Fibrwrap Construction Services, Inc. |
Shaun Loeding, Jason Alexander, Anna Pridmore, Structural Group, Inc. and Mark Geraghty |
Insituform Technologies, LLC and Aegion Corporation |
1:2013cv00176 |
January 16, 2013 |
US District Court for the District of Maryland |
Baltimore Office |
Anne Arundel |
Catherine C Blake |
Contract: Other |
28 U.S.C. § 1332 |
Plaintiff |
Docket Report
This docket was last retrieved on December 15, 2016. A more recent docket listing may be available from PACER.
Document Text |
---|
|
Magistrate Judge J. Mark Coulson no longer assigned to case. (hmls, Deputy Clerk) |
Filing 206 REPLY to Response to Motion re #200 MOTION for Reconsideration re #198 Memorandum Opinion Plaintiffs' Reply Memorandum in Support of Motion for Reconsideration filed by Fibrwrap Construction Services USA, Inc., Fibrwrap Construction Services, Inc., Fyfe Co., LLC. (Riley, Eileen) |
|
|
Filing 203 RESPONSE in Opposition re #200 MOTION for Reconsideration re #198 Memorandum Opinion filed by Jason Alexander, Mark Geraghty, Shaun Loeding, Anna Pridmore, Structural Group, Inc.. Replies due by 10/28/2016. (Taylor, Ronald) |
Filing 202 Correspondence re: dates for mediation Associated Cases: 1:13-cv-00176-CCB, 1:14-cv-00078-CCB(Riley, Eileen) |
|
Filing 200 MOTION for Reconsideration re #198 Memorandum Opinion by Fibrwrap Construction Services USA, Inc., Fibrwrap Construction Services, Inc., Fyfe Co., LLC Responses due by 10/11/2016 (Attachments: #1 Memorandum, #2 Text of Proposed Order)(Riley, Eileen) |
|
Filing 198 MEMORANDUM. Signed by Chief Judge Catherine C. Blake on 9/7/2016. (hmls, Deputy Clerk) |
Filing 197 NOTICE of Change of Address by Daniel E Farrington (Farrington, Daniel) |
Filing 196 MOTION to Seal Reply & Exhibits Filed in Support of Defendants' Motion for Summary Judgment by Jason Alexander, Mark Geraghty, Shaun Loeding, Anna Pridmore, Structural Group, Inc. Responses due by 10/13/2015 (Attachments: #1 Text of Proposed Order)(Taylor, Ronald) |
Filing 195 -SEALED-REPLY to Response to Motion re #182 MOTION for Summary Judgment filed by Jason Alexander, Mark Geraghty, Shaun Loeding, Anna Pridmore, Structural Group, Inc.. (Attachments: #1 Exhibit Supplemental 4, #2 Exhibit Supplemental 43, #3 Exhibit Supplemental 44, #4 Exhibit 94, #5 Exhibit 95, #6 Exhibit 95-A, #7 Exhibit 96, #8 Exhibit 97, #9 Exhibit 98, #10 Exhibit 99, #11 Exhibit 100, #12 Exhibit 101, #13 Exhibit 102, #14 Exhibit 103)(Taylor, Ronald) |
Filing 194 REPLY to Response to Motion re #177 MOTION to Strike #173 MOTION for Partial Summary Judgment Exhibits 1 and 13 filed by Jason Alexander, Mark Geraghty, Shaun Loeding, Anna Pridmore, Structural Group, Inc.. (Taylor, Ronald) |
|
Filing 192 Joint MOTION for Extension of Time to File Response/Reply as to #188 Response in Opposition to Motion, by Structural Group, Inc. Responses due by 9/28/2015 (Chammas, Daniel) |
Filing 191 MOTION to Seal Memorandum in Further Support of Plaintiffs' Motion for Partial Summary Judgment and in Opposition to Defendants' Motion for Summary Judgment, or in the Alternative, Partial Summary Judgment, and Exhibits by Fibrwrap Construction Services USA, Inc., Fibrwrap Construction Services, Inc., Fyfe Co., LLC Responses due by 9/21/2015 (Riley, Eileen) |
Filing 190 -SEALED-RESPONSE in Support re #173 MOTION for Partial Summary Judgment Memorandum of Law in Further Support of Plaintiffs' Motion of Partial Summary Judgment, RESPONSE in Opposition re #182 MOTION for Summary Judgment Memorandum in Opposition to Defendants' Motion for Summary Judgment or, in the Alternative, Partial Summary Judgment ( Replies due by 9/21/2015.) filed by Fibrwrap Construction Services USA, Inc., Fibrwrap Construction Services, Inc., Fyfe Co., LLC. (Attachments: #1 Exhibit Supplemental 3, 4, 5, 9, 10, 15, 18, #2 Exhibit 38-52, #3 Exhibit 53-55, #4 Exhibit 56-70)(Riley, Eileen) |
Filing 189 MOTION to Seal Plaintiffs' Opposition to Defendants' Motion to Strike the Declarations of Brian J. Clarke and John Huhn by Fibrwrap Construction Services USA, Inc., Fibrwrap Construction Services, Inc., Fyfe Co., LLC Responses due by 9/21/2015 (Riley, Eileen) |
Filing 188 -SEALED-RESPONSE in Opposition re #177 MOTION to Strike #173 MOTION for Partial Summary Judgment Exhibits 1 and 13 Plaintiffs' Opposition to the Motion to Strike the Declarations of Brian J. Clarke and John Huhn filed by Fibrwrap Construction Services USA, Inc., Fibrwrap Construction Services, Inc., Fyfe Co., LLC. Replies due by 9/21/2015. (Riley, Eileen) |
|
Filing 186 Consent MOTION for Extension of Time to Extend Deadline for Plaintiffs' Response to Defendants' Motion to Strike the Declarations of Brian J. Clarke and John Huhn by Fyfe Co., LLC Responses due by 8/27/2015 (Riley, Eileen) |
Filing 185 MOTION to Seal Memorandum and Exhibits 1-93 in Support of Motion for Summary Judgment by Jason Alexander, Mark Geraghty, Shaun Loeding, Anna Pridmore, Structural Group, Inc. Responses due by 8/20/2015 (Attachments: #1 Text of Proposed Order)(Taylor, Ronald) |
Filing 184 -SEALED - NOTICE of Filing Under Seal Notice of Filing Under Seal Exhibits 1-93 in Support of Motion for Summary Judgment by Jason Alexander, Mark Geraghty, Shaun Loeding, Anna Pridmore, Structural Group, Inc. re #182 MOTION for Summary Judgment (Attachments: #1 Exhibit 1, #2 Exhibit 2, #3 Exhibit 3, #4 Exhibit 4, #5 Exhibit 5, #6 Exhibit 6, #7 Exhibit 7, #8 Exhibit 7-A, #9 Exhibit 7-B, #10 Exhibit 8, #11 Exhibit 9, #12 Exhibit 10, #13 Exhibit 11, #14 Exhibit 11-A, #15 Exhibit 11-B, #16 Exhibit 12, #17 Exhibit 13, #18 Exhibit 13-A, #19 Exhibit 13-B, #20 Exhibit 13-C, #21 Exhibit 13-D, #22 Exhibit 14, #23 Exhibit 14-A, #24 Exhibit 14-B, #25 Exhibit 14-C, #26 Exhibit 15, #27 Exhibit 15-A, #28 Exhibit 15-B, #29 Exhibit 15-C, #30 Exhibit 15-D, #31 Exhibit 15-E, #32 Exhibit 15-F, #33 Exhibit 16, #34 Exhibit 16-A, #35 Exhibit 16-B, #36 Exhibit 17, #37 Exhibit 18, #38 Exhibit 19, #39 Exhibit 20, #40 Exhibit 21, #41 Exhibit 22, #42 Exhibit 23, #43 Exhibit 24, #44 Exhibit 25, #45 Exhibit 26, #46 Exhibit 27, #47 Exhibit 28, #48 Exhibit 29, #49 Exhibit 30, #50 Exhibit 31, #51 Exhibit 32, #52 Exhibit 33, #53 Exhibit 34, #54 Exhibit 35, #55 Exhibit 36, #56 Exhibit 37, #57 Exhibit 38, #58 Exhibit 39, #59 Exhibit 40, #60 Exhibit 41, #61 Exhibit 42, #62 Exhibit 43, #63 Exhibit 44, #64 Exhibit 45, #65 Exhibit 45-A, #66 Exhibit 45-B, #67 Exhibit 45-C, #68 Exhibit 45-D, #69 Exhibit 45-E, #70 Exhibit 45-F, #71 Exhibit 45-G, #72 Exhibit 45-H, #73 Exhibit 45-I, #74 Exhibit 45-J, #75 Exhibit 45-K, #76 Exhibit 46, #77 Exhibit 47, #78 Exhibit 48, #79 Exhibit 49, #80 Exhibit 50, #81 Exhibit 51, #82 Exhibit 52, #83 Exhibit 52-a, #84 Exhibit 53, #85 Exhibit 54, #86 Exhibit 55, #87 Exhibit 56, #88 Exhibit 57, #89 Exhibit 58, #90 Exhibit 59, #91 Exhibit 60, #92 Exhibit 61, #93 Exhibit 62, #94 Exhibit 63, #95 Exhibit 64, #96 Exhibit 65, #97 Exhibit 66, #98 Exhibit 67, #99 Exhibit 68, #100 Exhibit 69, #101 Exhibit 70, #102 Exhibit 71, #103 Exhibit 72, #104 Exhibit 73, #105 Exhibit 74, #106 Exhibit 75, #107 Exhibit 76, #108 Exhibit 77, #109 Exhibit 77-A, #110 Exhibit 77-B, #111 Exhibit 77-C, #112 Exhibit 77-D, #113 Exhibit 77-E, #114 Exhibit 77-F, #115 Exhibit 77-G, #116 Exhibit 77-H, #117 Exhibit 77-I, #118 Exhibit 77-J, #119 Exhibit 78, #120 Errata 79, #121 Exhibit 80, #122 Exhibit 81, #123 Errata 82, #124 Exhibit 83, #125 Exhibit 84, #126 Exhibit 84-A, #127 Exhibit 84-B, #128 Exhibit 84-C, #129 Exhibit 84-D, #130 Exhibit 85, #131 Exhibit 86, #132 Exhibit 87, #133 Exhibit 88, #134 Exhibit 89, #135 Exhibit 90, #136 Exhibit 91, #137 Exhibit 92, #138 Exhibit 93)(Taylor, Ronald) |
Filing 183 -SEALED - NOTICE of Filing Under Seal Memorandum in Support of Motion for Summary Judgment and Opposition to Plaintiffs' Motion for Partial Summary Judgment by Jason Alexander, Mark Geraghty, Shaun Loeding, Anna Pridmore, Structural Group, Inc. re #182 MOTION for Summary Judgment (Taylor, Ronald) |
Filing 182 MOTION for Summary Judgment by Jason Alexander, Mark Geraghty, Shaun Loeding, Anna Pridmore, Structural Group, Inc. Responses due by 8/20/2015 (Attachments: #1 Notice of Filing Memorandum Under Seal, #2 Notice of Filing Exhibits Under Seal, #3 Request for Hearing, #4 Text of Proposed Order)(Taylor, Ronald) |
Filing 181 MOTION to Seal Memorandum and Exhibits A & B in Support of Motion to Strike by Jason Alexander, Mark Geraghty, Shaun Loeding, Anna Pridmore, Structural Group, Inc. Responses due by 8/20/2015 (Attachments: #1 Text of Proposed Order)(Taylor, Ronald) |
Filing 180 -SEALED - NOTICE of Filing Under Seal Exhibit B to Memorandum in Support of Motion to Strike by Jason Alexander, Mark Geraghty, Shaun Loeding, Anna Pridmore, Structural Group, Inc. (Taylor, Ronald) |
Filing 179 -SEALED - NOTICE of Filing Under Seal Exhibit A to Memorandum in Support of Motion to Strike by Jason Alexander, Mark Geraghty, Shaun Loeding, Anna Pridmore, Structural Group, Inc. (Taylor, Ronald) |
Filing 178 -SEALED - NOTICE of Filing Under Seal Memorandum in Support of Defendants' Motion to Strike by Jason Alexander, Mark Geraghty, Shaun Loeding, Anna Pridmore, Structural Group, Inc. (Taylor, Ronald) |
Filing 177 MOTION to Strike #173 MOTION for Partial Summary Judgment Exhibits 1 and 13 by Jason Alexander, Mark Geraghty, Shaun Loeding, Anna Pridmore, Structural Group, Inc. Responses due by 8/20/2015 (Attachments: #1 Exhibit Notice of Filing Memorandum Under Seal, #2 Exhibit Notice of Filing Exhibits Under Seal, #3 Request for Hearing, #4 Text of Proposed Order)(Taylor, Ronald) |
Filing 176 MOTION to Seal Memorandum and Exhibits 1-37 in Support of Motion for Partial Summary Judgment by Fibrwrap Construction Services USA, Inc., Fibrwrap Construction Services, Inc., Fyfe Co., LLC Responses due by 7/20/2015 (Riley, Eileen) |
Filing 175 -SEALED - NOTICE of Filing Under Seal Exhibits 1-37 of Memorandum in Support of Motion for Partial Summary Judgment by Fibrwrap Construction Services USA, Inc., Fibrwrap Construction Services, Inc., Fyfe Co., LLC re #173 MOTION for Partial Summary Judgment (Attachments: #1 Exhibit 1-Declaration of Brian J. Clarke without attachments, #2 Exhibit 2-Declaration of Kent Bartholomew, #3 Exhibit 3-Excerpt from Deposition of Peter Emmons June 13, 2013, #4 Exhibit 4-Excerpt from Deposition of Jamie Lee Thomas, #5 Exhibit 5-Excerpt from Deposition of Brian Clarke, #6 Exhibit 6-Excerpt from Deposition of Jason Alexander, #7 Exhibit 7-Action by Consent of the Board of Directors, #8 Exhibit 8-Declaration of Tate Mitchell, #9 Exhibit 9-Excerpt from Deposition of Mark Geraghty, #10 Exhibit 10-Excerpt from Deposition of Shaun Loeding, #11 Exhibit 11-Executive Employment Agreement Jason Alexander, #12 Exhibit 12-Excerpt from Acquisition Agreement, #13 Exhibit 13-Declaration of John Huhn, #14 Exhibit 14-Bonus Program and Payment Schedule Letter to Jason Alexander, #15 Exhibit 15-Excerpt from Deposition of Anna Pridmore, #16 Exhibit 16-Structural Offer Letters to Jason Alexander, Mark Geraghty, Shaun Loeding and Anna Pridmore, #17 Exhibit 17-Jason Alexanders Objections and Responses to Plaintiffs First Set of Interrogatories, #18 Exhibit 18-Excerpt from Deposition of Peter Emmons February 17, 2015, #19 Exhibit 19-Letter re Resignation from Tod ODonoghue to Jason Alexander, Mark Geraghty, Shaun Loeding and Anna Pridmore, #20 Exhibit 20-Second Declaration of Michael Bandemer September 16, 2013, #21 Exhibit 21-Anna Pridmore Hot List 10-05-12, #22 Exhibit 22-Excerpt from Deposition of Michael Bandemer, #23 Exhibit 23-LNK files created on Anna Pridmores personal computer, #24 Exhibit 24-Hotlist Timeline, #25 Exhibit 25-Declaration of Michael Bandemer January 15, 2013, #26 Exhibit 26-Anna Pridmore email re: the computer program cc cleaner, #27 Exhibit 27-December 6, 2012 APS Cholla Bid, #28 Exhibit 28-July 20, 2012 APS Cholla Bid, #29 Exhibit 29-December 4, 2012 Email from Scott Arnold re: license letter, #30 Exhibit 30-November 16, 2012 Proposal re 303 East 51st Street, #31 Exhibit 31-Structural Group, Inc.s Answer to Defendant Fyfe Co., LLCs First Set of Interrogatories, #32 Exhibit 32-November 15, 2012 Email from Jason Alexander to Jay Thomas, #33 Exhibit 33-December 7, 2012 Email from Jason Alexander to Jay Thomas, #34 Exhibit 34-Shaun Loeding / Triton Construction Company emails re: 303 East 51st Street, #35 Exhibit 35-Excerpt from Deposition of Patrick Kennedy, #36 Exhibit 36-Report of Patrick F. Kennedy, Ph.D. April 11, 2014, #37 Exhibit 37-Structural Group, Inc. FRP Revenue and Gross Margin)(Riley, Eileen) |
Filing 174 -SEALED - NOTICE of Filing Under Seal Memorandum in Support of Motion for Parial Summary Judgment by Fibrwrap Construction Services USA, Inc., Fibrwrap Construction Services, Inc., Fyfe Co., LLC re #173 MOTION for Partial Summary Judgment (Attachments: #1 Exhibit Memorandum in Support of Motion for Partial Summary Judgment)(Riley, Eileen) |
Filing 173 MOTION for Partial Summary Judgment by Fibrwrap Construction Services USA, Inc., Fibrwrap Construction Services, Inc., Fyfe Co., LLC Responses due by 7/20/2015 (Attachments: #1 Exhibit Notice of Filing Memorandum Under Seal, #2 Exhibit Notice fof Filing Exhibits Under Seal, #3 Text of Proposed Order)(Riley, Eileen) |
Filing 172 RESPONSE in Opposition re #171 MOTION for Leave to File Sur-Reply filed by Structural Group, Inc.. Replies due by 6/25/2015. (Taylor, Ronald) |
Filing 171 MOTION for Leave to File Sur-Reply by Fibrwrap Construction Services USA, Inc., Fibrwrap Construction Services, Inc., Fyfe Co., LLC Responses due by 6/8/2015 (Attachments: #1 Attachment, #2 Exhibit 1)(Riley, Eileen) |
Filing 170 REPLY to Response to Motion re #166 MOTION for Reconsideration re #144 Order and to Compel Compliance with the Court's Order filed by Structural Group, Inc.. (Attachments: #1 Exhibit A)(Taylor, Ronald) |
|
Filing 168 RESPONSE in Opposition re #166 MOTION for Reconsideration re #144 Order and to Compel Compliance with the Court's Order filed by Fyfe Co., LLC. Replies due by 5/18/2015. (Attachments: #1 Exhibit A)(Riley, Eileen) |
Filing 167 Joint MOTION for Other Relief to Establish Briefing Schedule by Structural Group, Inc. Responses due by 5/18/2015 (Attachments: #1 Text of Proposed Order)(Chammas, Daniel) |
Filing 166 MOTION for Reconsideration re #144 Order and to Compel Compliance with the Court's Order by Structural Group, Inc. Responses due by 5/14/2015 (Attachments: #1 Memorandum of Points and Authorities, #2 Exhibit A to Memorandum of Points and Authorities, #3 Exhibit B to Memorandum of Points and Authorities, #4 Text of Proposed Order)(Chammas, Daniel) |
|
Filing 164 Correspondence re: Motion to Amend/Correct Scheduling Order (ECF No. 152) (Attachments: #1 Text of Proposed Order)(Chammas, Daniel) |
Magistrate Judge J. Mark Coulson no longer assigned to case. (hmls, Deputy Clerk) |
Filing 163 STATUS REPORT re Joint Discovery Deadline by Fibrwrap Construction Services USA, Inc., Fibrwrap Construction Services, Inc., Fyfe Co., LLC. (Silvestri, Stephen) |
|
|
Discovery Telephone Conference held on 3/25/2015 before Magistrate Judge J. Mark Coulson. (hmls, Deputy Clerk) |
|
Filing 159 RESPONSE re #148 Local Rule,, #157 Response, Defendant Structural Group, Inc.'s Reply Memorandum In Support Of Its Motion to Compel Document Production filed by Structural Group, Inc.. (Levin, Jennifer) |
|
Filing 157 RESPONSE re #148 Local Rule,, Non-Parties Aegion Corporation and Insituform Technologies, LLC's Opposition to Defendant Structural Group's Motion to Compel Document Production filed by Insituform Technologies, LLC, Aegion Corporation. (Attachments: #1 Exhibit A, #2 Exhibit B)(Riley, Eileen) |
Filing 156 (FILED IN ERROR - INCORRECT EVENT) MOTION Non-Parties Aegion Corporation and Insituform Technologies, LLC's Opposition to Defendant Structural Group's Motion to Compel Document Production by Aegion Corporation, Insituform Technologies, LLC Responses due by 4/6/2015 (Attachments: #1 Exhibit A, #2 Exhibit B)(Riley, Eileen) Modified on 3/20/2015 (hmls, Deputy Clerk). |
Filing 155 REPLY to Response to Motion re #149 MOTION to Strike the Untimely Expert Reports of Patrick F. Kennedy, Ph.D., and Michael Bandemer filed by Structural Group, Inc.. (Attachments: #1 Text of Proposed Order)(Levin, Jennifer) |
Filing 154 RESPONSE in Opposition re #149 MOTION to Strike the Untimely Expert Reports of Patrick F. Kennedy, Ph.D., and Michael Bandemer filed by Fibrwrap Construction Services USA, Inc., Fibrwrap Construction Services, Inc., Fyfe Co., LLC. Replies due by 4/6/2015. (Attachments: #1 Text of Proposed Order)(Kresslein, Charles) |
Filing 153 QC NOTICE: #152 Motion to Amend/Correct filed by Structural Group, Inc. was filed incorrectly. **Each document must be scanned individually into separate PDF documents. Your exhibits were scanned into a single PDF with the motion. For future reference, please file exhibits separately as attachments. (hmls, Deputy Clerk) |
Filing 152 MOTION to Amend/Correct 137 Order on Motion to Amend/Correct Scheduling Order by Structural Group, Inc. Responses due by 4/6/2015 (Chammas, Daniel) |
|
Filing 150 Emergency MOTION to Expedite Plaintiffs' Deadline to Oppose Structural's Motion to Strike the Untimely Expert Reports of Patrick F. Kennedy, Ph.D., and Michael Bandemer by Structural Group, Inc. Responses due by 4/2/2015 (Strong, Thomas) |
Filing 149 MOTION to Strike the Untimely Expert Reports of Patrick F. Kennedy, Ph.D., and Michael Bandemer by Structural Group, Inc. Responses due by 4/2/2015 (Attachments: #1 Supplement Memorandum in Support of Motion)(Strong, Thomas) |
Filing 148 Local Rule 104.8 Certificate of Conference. (Attachments: #1 Structural Group, Inc. Motion to Compel, #2 Structural Group, Inc. Memorandum ISO Motion to Compel, #3 Exhibit 1 to SGI Memo ISO Motion to Compel, #4 Exhibit 2 to SGI Memo ISO Motion to Compel, #5 Exhibit 3 to SGI Memo ISO Motion to Compel, #6 Exhibit 4 to SGI Memo ISO Motion to Compel, #7 Exhibit 5 to SGI Memo ISO Motion to Compel, #8 Exhibit 6 to SGI Memo ISO Motion to Compel, #9 Exhibit 7 to SGI Memo ISO Motion to Compel, #10 Exhibit 8 to SGI Memo ISO Motion to Compel, #11 Text of Proposed Order re SGI Memo ISO Motion to Compel)(Levin, Jennifer) |
Filing 147 LETTER OPINION re: Plaintiffs' #145 Motion to Compel submitted in accordance with Local Rule 104.7; Denying motion as to Request for Production of Documents No. 20 and Interrogatories Nos. 25 and 26 and Found Moot as to Plaintiffs' other requests. Signed by Magistrate Judge J. Mark Coulson on 2/9/2015. (dass, Deputy Clerk) |
Discovery Telephone Conference held on 2/9/2015 before Magistrate Judge J. Mark Coulson. (ca2s, Deputy Clerk) |
|
Filing 145 Local Rule 104.7 Certificate in Support of Plaintiff's Motion to Compel. (Attachments: #1 Exhibit 1, #2 Exhibit 2, #3 Exhibit 3)(Kresslein, Charles) |
|
Filing 143 Correspondence re: (Kresslein, Charles) |
|
Filing 141 Local Rule 104.7 Certification. (Attachments: #1 Defendant Structural Group, Inc.'s Motion to Compel Discovery Responses and Document Production, #2 Structural Group, Inc.'s Memorandum in Support of Motion to Compel Discovery Responses and Document Production, #3 Ex A - Structural Group, Inc.'s Memorandum in Support of Motion to Compel Discovery Responses and Document Production, #4 Ex B - Structural Group, Inc.'s Memorandum in Support of Motion to Compel Discovery Responses and Document Production, #5 Ex C - Structural Group, Inc.'s Memorandum in Support of Motion to Compel Discovery Responses and Document Production, #6 Ex D - Structural Group, Inc.'s Memorandum in Support of Motion to Compel Discovery Responses and Document Production, #7 Ex E - Structural Group, Inc.'s Memorandum in Support of Motion to Compel Discovery Responses and Document Production, #8 Ex F - Structural Group, Inc.'s Memorandum in Support of Motion to Compel Discovery Responses and Document Production, #9 Ex G - Structural Group, Inc.'s Memorandum in Support of Motion to Compel Discovery Responses and Document Production, #10 Ex H - Structural Group, Inc.'s Memorandum in Support of Motion to Compel Discovery Responses and Document Production, #11 Ex I - Structural Group, Inc.'s Memorandum in Support of Motion to Compel Discovery Responses and Document Production, #12 Ex J - Structural Group, Inc.'s Memorandum in Support of Motion to Compel Discovery Responses and Document Production, #13 Ex K - Structural Group, Inc.'s Memorandum in Support of Motion to Compel Discovery Responses and Document Production, #14 Ex L - Structural Group, Inc.'s Memorandum in Support of Motion to Compel Discovery Responses and Document Production, #15 Ex M - Structural Group, Inc.'s Memorandum in Support of Motion to Compel Discovery Responses and Document Production, #16 Ex N - Structural Group, Inc.'s Memorandum in Support of Motion to Compel Discovery Responses and Document Production, #17 Ex O - Structural Group, Inc.'s Memorandum in Support of Motion to Compel Discovery Responses and Document Production, #18 Plaintiff's Opposition to Defendant Structural Group's Motion to Compel Discovery Responses and Document Production, #19 Defendant Structural Group, Inc.'s Reply in Support of its Motion to Compel Discovery Responses and Document Production, #20 Ex 1 - Defendant Structural Group, Inc.'s Reply in Support of its Motion to Compel Discovery Responses and Document Production, #21 Ex 2 - Defendant Structural Group, Inc.'s Reply in Support of its Motion to Compel Discovery Responses and Document Production)(Taylor, Ronald) |
Filing 140 Correspondence re: (Kresslein, Charles) |
|
Filing 138 STIPULATION of Dismissal of Count VI Without Prejudice (JOINT) by Fibrwrap Construction Services USA, Inc., Fibrwrap Construction Services, Inc., Fyfe Co., LLC. (Riley, Eileen) |
|
Filing 136 Joint MOTION to Amend/Correct #129 Scheduling Order by Fibrwrap Construction Services USA, Inc., Fibrwrap Construction Services, Inc., Fyfe Co., LLC Responses due by 1/5/2015 (Silvestri, Stephen) |
|
Filing 134 Correspondence re: Deposition Topics (Riley, Eileen) |
Telephone Conference re: discovery dispute held on 11/20/2014 before Magistrate Judge J. Mark Coulson. (nd2, Deputy Clerk) |
Filing 133 Correspondence re: deposition subjects (Biran, Sarah) |
Filing 132 RESPONSE re #131 Status Report, Defendant Structural Group, Inc.'s Memorandum Regarding Topics in Revised Notice of Deposition of Plaintiffs filed by All Plaintiffs. (Kresslein, Charles) |
Filing 131 STATUS REPORT Defendant Structural Group, Inc.'s Memorandum Regarding Topics in Revised Notice of Deposition of Plaintiffs by Structural Group, Inc.. (Attachments: #1 Exhibit A, #2 Exhibit B, #3 Exhibit C, #4 Exhibit D)(Levin, Jennifer) |
|
Status Conference held on 10/31/2014 before Magistrate Judge J. Mark Coulson. (cags, Deputy Clerk) |
Telephone Status Conference held on 10/17/2014 before Magistrate Judge J. Mark Coulson. (cags, Deputy Clerk) |
|
Filing 128 STIPULATION re Proposed Scheduling Order by Fibrwrap Construction Services USA, Inc., Fibrwrap Construction Services, Inc., Fyfe Co., LLC. (Silvestri, Stephen) |
Filing 127 ANSWER to #67 Amended Complaint by Jason Alexander, Mark Geraghty, Shaun Loeding, Anna Pridmore, Structural Group, Inc..(Strong, Thomas) |
Filing 126 STATUS REPORT Joint by Fibrwrap Construction Services USA, Inc., Fibrwrap Construction Services, Inc., Fyfe Co., LLC. (Riley, Eileen) |
Case reassigned to Magistrate Judge J. Mark Coulson. Magistrate Judge Susan K. Gauvey no longer assigned to the case. (jnls, Deputy Clerk) |
|
Filing 124 MEMORANDUM. Signed by Judge Catherine C. Blake on 8/11/14. (mps, Deputy Clerk) |
Filing 123 REPLY to Response to Motion re #116 MOTION to Dismiss for Failure to State a Claimor, In The Alternative, for Judgment On The Pleadings filed by Jason Alexander, Mark Geraghty, Shaun Loeding, Anna Pridmore, Structural Group, Inc.. (Strong, Thomas) |
Filing 122 RESPONSE to Motion re #116 MOTION to Dismiss for Failure to State a Claimor, In The Alternative, for Judgment On The Pleadings filed by Fibrwrap Construction Services USA, Inc., Fibrwrap Construction Services, Inc., Fyfe Co., LLC. Replies due by 6/23/2014. (Attachments: #1 Text of Proposed Order)(Kresslein, Charles) |
Filing 121 NOTICE of Appearance by Charles Joseph Kresslein on behalf of Fibrwrap Construction Services USA, Inc., Fibrwrap Construction Services, Inc., Fyfe Co., LLC (Kresslein, Charles) |
|
|
Filing 118 MOTION for Extension of Time to File Response/Reply as to #116 MOTION to Dismiss for Failure to State a Claimor, In The Alternative, for Judgment On The Pleadings by Fibrwrap Construction Services USA, Inc., Fibrwrap Construction Services, Inc., Fyfe Co., LLC Responses due by 6/16/2014 (Attachments: #1 Text of Proposed Order)(Riley, Eileen) |
Filing 117 Joint MOTION for Extension of Time to Complete Discovery and Modify Scheduling Order by Structural Group, Inc. Responses due by 6/16/2014 (Attachments: #1 Text of Proposed Order)(Strong, Thomas) |
Filing 116 MOTION to Dismiss for Failure to State a Claimor, In The Alternative, for Judgment On The Pleadings by Jason Alexander, Mark Geraghty, Shaun Loeding, Anna Pridmore, Structural Group, Inc. Responses due by 6/2/2014 (Attachments: #1 Defendants' Memorandum of Law In Support Of Their Motion to Dismiss or, In The Alternative, For Judgment On The Pleadings, #2 Text of Proposed Order)(Chammas, Daniel) |
|
|
|
Telephone Conference held on 4/2/2014 before Magistrate Judge Susan K. Gauvey. (FTR Jill Klein -5A.) (jks, Deputy Clerk) |
|
Filing 111 MOTION to Seal Additional Documents Filed in Support of Plaintiffs' Motion to Expedite Discovery Regarding Spoliation of Defendant Structural Group, Inc.'s Evidence by Fibrwrap Construction Services USA, Inc., Fibrwrap Construction Services, Inc., Fyfe Co., LLC Responses due by 4/18/2014 (Riley, Eileen) |
Filing 110 Sealed Document. (Attachments: #1 Exhibit Letter to Magistrate Gauvey and Deposition of Tarek Alkhrdaji)(Riley, Eileen) |
Filing 109 [FILED IN ERROR] Correspondence re: Upcoming Conference Call (Attachments: #1 Deposition of Dr. Tarek Alkhrdaji)(Riley, Eileen) Modified on 4/1/2014 (mps, Deputy Clerk). |
|
Filing 107 REPLY to Response to Motion re #102 MOTION to Expedite Discovery Regarding Spoliation of Defendant Structural Group, Inc.'s Evidence filed by Fibrwrap Construction Services USA, Inc., Fibrwrap Construction Services, Inc., Fyfe Co., LLC. (Attachments: #1 Exhibit 17)(Riley, Eileen) |
Filing 106 RESPONSE in Opposition re #102 MOTION to Expedite Discovery Regarding Spoliation of Defendant Structural Group, Inc.'s Evidence filed by Structural Group, Inc.. Replies due by 4/10/2014. (Levin, Jennifer) |
|
|
Filing 103 MOTION to Seal Documents Filed in Support of Plaintiffs' Motion to Expedite Discovery Regarding Spoliation of Defendant Structural Group, Inc.'s Evidence by Fibrwrap Construction Services USA, Inc., Fibrwrap Construction Services, Inc., Fyfe Co., LLC Responses due by 3/24/2014 (Riley, Eileen) |
Filing 102 -SEALED- MOTION to Expedite Discovery Regarding Spoliation of Defendant Structural Group, Inc.'s Evidence by Fibrwrap Construction Services USA, Inc., Fibrwrap Construction Services, Inc., Fyfe Co., LLC Responses due by 3/24/2014 (Attachments: #1 Memorandum in Support, #2 Exhibit 1, #3 Exhibit 2, #4 Exhibit 3, #5 Exhibit 4, #6 Exhibit 5, #7 Exhibit 6, #8 Exhibit 7, #9 Exhibit 8, #10 Exhibit 9, #11 Exhibit 10, #12 Exhibit 11, #13 Exhibit 12, #14 Exhibit 13, #15 Exhibit 14, #16 Exhibit 15, #17 Exhibit 16, #18 Proposed Order)(Riley, Eileen) |
Filing 101 Correspondence re: spoliation of Dr. Alkhradji's computer (Riley, Eileen) |
Filing 100 Correspondence re: (Levin, Jennifer) |
|
Filing 98 MEMORANDUM. Signed by Magistrate Judge Susan K. Gauvey on 2/10/14. (mps, Deputy Clerk) |
|
Reset Deadlines: Status Report due by 6/30/2014. (dass, Deputy Clerk) |
Filing 96 Correspondence re: Related Action (Strong, Thomas) |
Filing 95 Joint MOTION for Extension of Time by Fibrwrap Construction Services USA, Inc., Fibrwrap Construction Services, Inc., Fyfe Co., LLC Responses due by 1/27/2014 (Attachments: #1 Proposed Order)(Riley, Eileen) |
|
Filing 93 STATUS REPORT by Fibrwrap Construction Services USA, Inc., Fibrwrap Construction Services, Inc., Fyfe Co., LLC. (Riley, Eileen) |
Filing 92 Joint MOTION for Extension of Time for Submitting Status Report by Fibrwrap Construction Services USA, Inc., Fibrwrap Construction Services, Inc., Fyfe Co., LLC Responses due by 1/24/2014 (Riley, Eileen) |
|
Case Stayed (mps, Deputy Clerk) |
Filing 90 Joint Correspondence re: suspension of deadlines for settlement discussions (Silvestri, Stephen) |
Filing 89 MOTION to Seal Documents Filed in Support of Plaintiffs' Reply to Defendant's Opposition to the Designation of Dr. Tarek Alkhradji as an Additional Custodian Under Expedited Discovery Plan by Fibrwrap Construction Services USA, Inc., Fibrwrap Construction Services, Inc., Fyfe Co., LLC Responses due by 11/25/2013 (Riley, Eileen) |
Filing 88 -SEALED-RESPONSE in Opposition re #80 MOTION to Compel Designation of Dr. Tarek Alkhradji as Additionon Custodian Under Expedited Discovery Plan ( Replies due by 11/25/2013.), REPLY to Response to Motion re #80 MOTION to Compel Designation of Dr. Tarek Alkhradji as Additionon Custodian Under Expedited Discovery Plan filed by Fibrwrap Construction Services USA, Inc., Fibrwrap Construction Services, Inc., Fyfe Co., LLC. (Attachments: #1 Exhibit)(Riley, Eileen) |
|
Filing 86 MOTION to Seal DEFENDANT STRUCTURALS OPPOSITION TO PLAINTIFFS MOTION TO COMPEL DESIGNATION OF DR. TAREK ALKHRDAJI AS ADDITIONAL CUSTODIAN UNDER EXPEDITED DISCOVERY PLAN by Structural Group, Inc. Responses due by 11/7/2013 (Attachments: #1 Text of Proposed Order SEALING DEFENDANT STRUCTURAL GROUP, INC.S OPPOSITION TO PLAINTIFFS MOTION TO COMPEL DESIGNATION OF DR. TAREK ALKHRDAJI AS ADDITIONAL CUSTODIAN UNDER EXPEDITED DISCOVERY PLAN)(Levin, Jennifer) |
Filing 85 RESPONSE in Opposition re #80 MOTION to Compel Designation of Dr. Tarek Alkhradji as Additionon Custodian Under Expedited Discovery Plan filed by Structural Group, Inc.. Replies due by 11/7/2013. (Attachments: #1 Affidavit Declaration of Daniel B. Chammas, #2 Affidavit Declaration of Dr. Tarek Alkhrdaji)(Levin, Jennifer) |
|
|
Filing 82 Joint MOTION for Extension of Time by Fibrwrap Construction Services USA, Inc., Fibrwrap Construction Services, Inc., Fyfe Co., LLC Responses due by 10/24/2013 (Attachments: #1 Order)(Riley, Eileen) |
Filing 81 MOTION to Seal Documents Filed in Support of Plaintiffs' Motion to Compel Designation of Dr. Tarek Alkhradji as Additional Custodian Under Expedited Discovery Plan by Fibrwrap Construction Services USA, Inc., Fibrwrap Construction Services, Inc., Fyfe Co., LLC Responses due by 10/21/2013 (Riley, Eileen) |
Filing 80 -SEALED- MOTION to Compel Designation of Dr. Tarek Alkhradji as Additionon Custodian Under Expedited Discovery Plan by Fibrwrap Construction Services USA, Inc., Fibrwrap Construction Services, Inc., Fyfe Co., LLC Responses due by 10/21/2013 (Attachments: #1 Local Rule 104.7 Certification, #2 Memorandum in Support, #3 Exhibit 1, #4 Exhibit 2, #5 Exhibit 3, #6 Exhibit 4, #7 Exhibit 5, #8 Exhibit 6, #9 Exhibit 7, #10 Proposed Order)(Riley, Eileen) |
Filing 79 MOTION to Seal Exhibits to Reply in Support of Motion to Dismiss by Jason Alexander, Mark Geraghty, Shaun Loeding, Anna Pridmore Responses due by 10/21/2013 (Attachments: #1 Text of Proposed Order)(Biran, Sarah) |
Filing 78 -SEALED - NOTICE of Filing Under Seal Exhibits to Biran Declaration of October 3, 2013 by Jason Alexander, Mark Geraghty, Shaun Loeding, Anna Pridmore re #77 Reply to Response to Motion, (Attachments: #1 Exhibit confidential deposition excerpt, #2 Exhibit confidential deposition excerpt)(Biran, Sarah) |
Filing 77 REPLY to Response to Motion re #71 MOTION to Dismiss for Lack of Jurisdiction , #76 MOTION to Seal Plaintiffs' Opposition to Defendants' Motion to Dismiss Second Amended Complaint and Attached Exhibits and Plaintiffs' Opposition filed by Jason Alexander, Mark Geraghty, Shaun Loeding, Anna Pridmore. (Attachments: #1 Affidavit, #2 Exhibit, #3 Exhibit, #4 Exhibit)(Biran, Sarah) |
Filing 76 MOTION to Seal Plaintiffs' Opposition to Defendants' Motion to Dismiss Second Amended Complaint and Attached Exhibits by Fibrwrap Construction Services USA, Inc., Fibrwrap Construction Services, Inc., Fyfe Co., LLC Responses due by 10/3/2013 (Attachments: #1 Text of Proposed Order Proposed Order)(Silvestri, Stephen) |
Filing 75 -SEALED-RESPONSE in Opposition re #73 MOTION to Dismiss OF DEFENDANTS JASON ALEXANDER, MARK GERAGHTY, SHAUN LOEDING, AND ANNA PRIDMORE, #71 MOTION to Dismiss for Lack of Jurisdiction filed by Fibrwrap Construction Services USA, Inc., Fibrwrap Construction Services, Inc., Fyfe Co., LLC. Replies due by 10/3/2013. (Attachments: #1 Exhibit 1 - Depo Excerpts - Alexander, #2 Exhibit 2 - Depo Excerpts - Emmons, #3 Exhibit 3 - Depo Excerpts - Loeding, #4 Exhibit 4 - Depo Excerpts - Geraghty, #5 Exhibit 5 - Second Declaration of Mike Bandemer, #6 Exhibit 6 - Depo Excerpts - Pridmore, #7 Exhibit 7 - Depo Excerpts - Thomas)(Silvestri, Stephen) |
Filing 74 -SEALED - NOTICE of Filing Under Seal Exhibit A to Declaration of Sarah K. Biran by Jason Alexander, Mark Geraghty, Shaun Loeding, Anna Pridmore re #72 MOTION to Seal Documents in Filed in Support of Motion to Dismiss Second Amended Complaint, #71 MOTION to Dismiss for Lack of Jurisdiction (Attachments: #1 sealed exhibit, #2 sealed declaration, #3 sealed exhibit)(Biran, Sarah) |
Filing 73 MOTION to Dismiss OF DEFENDANTS JASON ALEXANDER, MARK GERAGHTY, SHAUN LOEDING, AND ANNA PRIDMORE by Structural Group, Inc. Responses due by 9/16/2013 (Levin, Jennifer) |
Filing 72 MOTION to Seal Documents in Filed in Support of Motion to Dismiss Second Amended Complaint by Jason Alexander, Mark Geraghty, Shaun Loeding, Anna Pridmore Responses due by 9/16/2013 (Attachments: #1 Text of Proposed Order)(Biran, Sarah) |
Filing 71 MOTION to Dismiss for Lack of Jurisdiction by Jason Alexander, Mark Geraghty, Shaun Loeding, Anna Pridmore Responses due by 9/16/2013 (Attachments: #1 Memorandum in Support, #2 Affidavit, #3 Exhibit, #4 Exhibit, #5 Affidavit, #6 Affidavit, #7 Exhibit, #8 Exhibit, #9 Text of Proposed Order)(Biran, Sarah) |
|
|
Filing 68 Consent MOTION for Extension of Time to File Answer re #67 Amended Complaint by Structural Group, Inc. Responses due by 8/29/2013 (Levin, Jennifer) |
Filing 67 SECOND AMENDED COMPLAINT against Jason Alexander, Mark Geraghty, Shaun Loeding, Anna Pridmore, Structural Group, Inc., filed by Fibrwrap Construction Services USA, Inc., Fyfe Co., LLC, Fibrwrap Construction Services, Inc..(mps, Deputy Clerk) |
|
Filing 65 RESPONSE re #64 MOTION for Leave to File Second Amended Complaint filed by Structural Group, Inc.. (Levin, Jennifer) |
Filing 64 MOTION for Leave to File Second Amended Complaint by Fibrwrap Construction Services USA, Inc., Fibrwrap Construction Services, Inc., Fyfe Co., LLC Responses due by 8/2/2013 (Attachments: #1 Exhibit Second Amended Complaint (redlined), #2 Exhibit Second Amended Complaint (clean), #3 Exhibit Memo of Law in Support of Motion for Leave to File Second Amended Complaint, #4 Text of Proposed Order Proposed Order)(Silvestri, Stephen) |
Telephone Conference re: Scheduling held on 7/11/2013 before Judge Catherine C. Blake. (kam, Deputy Clerk) |
|
Filing 62 Correspondence re: Court's proposed deadlines (Silvestri, Stephen) |
|
Telephone Conference held on 6/25/2013 before Magistrate Judge Susan K. Gauvey. (ER/Nadine Mitter). (nrm, Deputy Clerk) |
Filing 60 Miscellaneous Correspondence re: A conference call has been scheduled for July 11, 2013 at 9:00 a.m. to discuss the attached draft scheduling order. Chambers requests that plaintiffs' counsel arrange the conference call. (kys, Chambers) |
Filing 59 ANSWER to #13 Amended Complaint by Structural Group, Inc..(Strong, Thomas) |
|
Filing 57 MEMORANDUM. Signed by Judge Catherine C. Blake on 5/30/13. (dass, Deputy Clerk) |
Filing 56 REPLY to Response to Motion re #50 MOTION for Protective Order to Require Return of Documents and Memory Devices filed by Fibrwrap Construction Services USA, Inc., Fibrwrap Construction Services, Inc., Fyfe Co., LLC. (Silvestri, Stephen) |
|
Filing 54 Joint MOTION to Seal All Copies of the Private Label Agreement by Structural Group, Inc. Responses due by 5/24/2013 (Attachments: #1 Text of Proposed Order, #2 Affidavit Emmons)(Levin, Jennifer) |
Filing 53 RESPONSE in Opposition re #50 MOTION for Protective Order to Require Return of Documents and Memory Devices filed by Jason Alexander, Mark Geraghty, Shaun Loeding, Anna Pridmore, Structural Group, Inc.. Replies due by 5/23/2013. (Levin, Jennifer) |
|
Filing 51 Correspondence re: Stipulated Protective Order (Attachments: #1 Text of Proposed Order Stipulated Protective Order)(Silvestri, Stephen) |
Filing 50 MOTION for Protective Order to Require Return of Documents and Memory Devices by Fibrwrap Construction Services USA, Inc., Fibrwrap Construction Services, Inc., Fyfe Co., LLC Responses due by 5/6/2013 (Attachments: #1 Exhibit Memorandum of Law, #2 Exhibit Exhibit 1, #3 Exhibit Exhibit 2, #4 Exhibit Exhibit 3, #5 Exhibit Exhibit 4, #6 Exhibit Exhibit 5, #7 Exhibit Exhibit 6, #8 Exhibit Exhibit 7, #9 Exhibit Exhibit 8, #10 Text of Proposed Order Proposed Protective Order)(Silvestri, Stephen) |
Telephone Conference held on 4/8/2013 before Judge Catherine C. Blake. (kam, Deputy Clerk) |
Filing 49 Correspondence re: April 8, 2013 Conference Call (Strong, Thomas) |
Filing 48 Correspondence re: April 8, 2013 Conference Call (Silvestri, Stephen) |
Filing 47 PAPERLESS ORDER granting #46 Motion to Appear Pro Hac Vice on behalf of Jennifer Levin for Structural Group, Inc. Directing attorney Jennifer Levin to register online for CM/ECF at https://www.mdd.uscourts.gov/attyregB/inputProHac.asp. Signed by Clerk on 4/3/13. (cmns, Deputy Clerk) |
Filing 46 MOTION to Appear Pro Hac Vice for Jennifer Levin by Structural Group, Inc.($50 fee paid, receipt no. 14637066112) (mps, Deputy Clerk) |
Telephone Status Conference held on 4/1/2013 before Magistrate Judge Susan K. Gauvey. (mps, Deputy Clerk) |
Filing 45 PAPERLESS Correspondence to counsel: A conference call to discuss pending motions has been set for April 8, 2013 at 4:00 p.m. Plaintiffs' counsel is asked to initiate the call. (Blake, Catherine) |
|
Filing 43 Request for Conference (Attachments: #1 Exhibit A, #2 Exhibit B, #3 Exhibit C, #4 Exhibit D, #5 Exhibit E, #6 Exhibit F, #7 Exhibit G, #8 Exhibit H)(Riley, Eileen) |
Filing 42 Request for Conference (Riley, Eileen) |
Filing 41 REPLY to Response to Motion re #31 MOTION to Dismiss for Lack of Jurisdiction MOTION to Dismiss for Failure to State a Claim as to Count X filed by Jason Alexander, Mark Geraghty, Shaun Loeding, Anna Pridmore. (Attachments: #1 Affidavit)(Biran, Sarah) |
|
Telephone Status Conference held on 3/11/2013 before Magistrate Judge Susan K. Gauvey. (mps, Deputy Clerk) |
|
Filing 38 REPLY to Response to Motion re #18 MOTION for Leave to File Supplemental Memorandum of Law in Support of Plaintiffs' Motion for Temporary Restraining Order and Preliminary Injunction filed by Fibrwrap Construction Services USA, Inc., Fibrwrap Construction Services, Inc., Fyfe Co., LLC. (Silvestri, Stephen) |
Filing 37 QC NOTICE: #36 Response in Opposition filed by Fibrwrap Construction Services USA, Inc., Fibrwrap Construction Services, Inc., Fyfe Co., LLC was filed incorrectly. **This document is a reply and should be filed as a reply and linked back to the original motion. Please refile It has been noted as FILED IN ERROR, and the document link has been disabled. (mps, Deputy Clerk) |
Filing 36 [FILED IN ERROR] RESPONSE in Opposition re #32 Response in Opposition to Motion, by Fibrwrap Construction Services USA, Inc., Fibrwrap Construction Services, Inc., Fyfe Co., LLC. (Silvestri, Stephen) Modified on 3/5/2013 (mps, Deputy Clerk). |
Filing 35 RESPONSE in Opposition re #34 MOTION to Dismiss OF DEFENDANTS JASON ALEXANDER, MARK GERAGHTY, SHAUN LOEDING, AND ANNA PRIDMORE, #31 MOTION to Dismiss for Lack of Jurisdiction MOTION to Dismiss for Failure to State a Claim as to Count X filed by Fibrwrap Construction Services USA, Inc., Fibrwrap Construction Services, Inc., Fyfe Co., LLC. Replies due by 3/18/2013. (Attachments: #1 Exhibit 1 - Declaration of Tate Mitchell, #2 Exhibit 2 - Declaration of Brian Clarke, #3 Exhibit 3 - University of Miami CAE Web Page, #4 Exhibit 4 - Declaration of Eileen Riley)(Silvestri, Stephen) |
Filing 34 MOTION to Dismiss OF DEFENDANTS JASON ALEXANDER, MARK GERAGHTY, SHAUN LOEDING, AND ANNA PRIDMORE by Structural Group, Inc. Responses due by 3/11/2013 (Taylor, Ronald) |
|
Filing 32 RESPONSE in Opposition re #18 MOTION for Leave to File Supplemental Memorandum of Law in Support of Plaintiffs' Motion for Temporary Restraining Order and Preliminary Injunction filed by Jason Alexander. Replies due by 3/4/2013. (Attachments: #1 Exhibit)(Biran, Sarah) |
Filing 31 MOTION to Dismiss for Lack of Jurisdiction , MOTION to Dismiss for Failure to State a Claim as to Count X by Jason Alexander, Mark Geraghty, Shaun Loeding, Anna Pridmore Responses due by 2/28/2013 (Attachments: #1 Memorandum, #2 Text of Proposed Order)(Biran, Sarah) |
Filing 30 NOTICE of Appearance by Sarah K Biran on behalf of Mark Geraghty, Shaun Loeding, Anna Pridmore (Biran, Sarah) |
Filing 29 NOTICE of Appearance by Sarah K Biran on behalf of Jason Alexander (Biran, Sarah) |
Filing 28 PAPERLESS ORDER granting #27 Motion to Appear Pro Hac Vice on behalf of Daniel B Chammas for Structural Group, Inc. Directing attorney Daniel B Chammas to register on-line for CM/ECF at https://www.mdd.uscourts.gov/attyregB/inputProHac.asp. Signed by Clerk on 2/11/13. (cmns, Deputy Clerk) |
Filing 27 MOTION to Appear Pro Hac Vice for Daniel B. Chammas by Structural Group, Inc.($50 fee paid, receipt no. 14637064847) (mps, Deputy Clerk) |
Filing 26 Correspondence re: response to Plaintiffs' February 4, 2013 letter to Court regarding expedited discovery (Taylor, Ronald) |
Filing 25 STATUS REPORT Regarding Discovery Plan by Fibrwrap Construction Services USA, Inc., Fibrwrap Construction Services, Inc., Fyfe Co., LLC. (Cannon, Louis) |
|
Filing 23 Correspondence re: Stipulated Consent Order (Attachments: #1 Text of Proposed Order Stipulated Consent Order)(Silvestri, Stephen) |
Filing 22 NOTICE of Appearance by Daniel E Farrington on behalf of Jason Alexander, Mark Geraghty, Shaun Loeding, Anna Pridmore (Farrington, Daniel) |
Filing 21 STATUS REPORT by Fibrwrap Construction Services USA, Inc., Fibrwrap Construction Services, Inc., Fyfe Co., LLC. (Riley, Eileen) |
Filing 20 Supplemental Memorandum to #2 MOTION for Temporary Restraining Order MOTION for Preliminary Injunction filed by Fibrwrap Construction Services USA, Inc., Fibrwrap Construction Services, Inc., Fyfe Co., LLC. (Attachments: #1 Exhibit 1, #2 Exhibit A, #3 Exhibit B, #4 Exhibit C)(dass, Deputy Clerk) |
|
Telephone Conference held on 1/23/2013 before Judge Catherine C. Blake. (kams, Deputy Clerk) |
Filing 18 MOTION for Leave to File Supplemental Memorandum of Law in Support of Plaintiffs' Motion for Temporary Restraining Order and Preliminary Injunction by Fibrwrap Construction Services USA, Inc., Fibrwrap Construction Services, Inc., Fyfe Co., LLC Responses due by 2/11/2013 (Attachments: #1 Exhibit A (Supplemental Memorandum), #2 Exhibit 1 (Declaration of Tate Mitchell), #3 Exhibit A, #4 Exhibit B, #5 Exhibit C)(Riley, Eileen) |
|
Filing 16 Local Rule 103.3 Disclosure Statement by Fibrwrap Construction Services USA, Inc. identifying Other Affiliate Infrastructure Group Holdings, LLC, Other Affiliate Aegion Corporation for Fibrwrap Construction Services USA, Inc... (Riley, Eileen) |
Filing 15 Local Rule 103.3 Disclosure Statement by Fibrwrap Construction Services, Inc. identifying Other Affiliate Infrastructure Group Holdings, LLC, Other Affiliate Aegion Corporation for Fibrwrap Construction Services, Inc... (Riley, Eileen) |
Filing 14 Local Rule 103.3 Disclosure Statement by Fyfe Co., LLC identifying Other Affiliate Infrastructure Group Holdings, LLC, Other Affiliate Aegion Corporation for Fyfe Co., LLC.. (Riley, Eileen) |
Filing 13 AMENDED COMPLAINT against All Defendants, filed by Fibrwrap Construction Services USA, Inc., Fyfe Co., LLC, Fibrwrap Construction Services, Inc.. (Attachments: #1 Supplement Redlined-Amended Complaint)(Riley, Eileen) |
Filing 12 NOTICE of Appearance by Ronald W Taylor on behalf of Structural Group, Inc. (Taylor, Ronald) |
Filing 11 NOTICE of Appearance by Thomas H Strong on behalf of Structural Group, Inc. (Strong, Thomas) |
Filing 10 EXHIBIT LIST by Jason Alexander, Mark Geraghty, Shaun Loeding, Anna Pridmore, Structural Group, Inc. (Attachments: #1 Exhibit 1)(mps, Deputy Clerk) |
|
Filing 8 Motion Hearing held on 1/17/2013 re #2 MOTION for Temporary Restraining Order MOTION for Preliminary Injunction filed by Fibrwrap Construction Services USA, Inc., Fibrwrap Construction Services, Inc., Fyfe Co., LLC, #3 MOTION to Expedite filed by Fibrwrap Construction Services USA, Inc., Fibrwrap Construction Services, Inc., Fyfe Co., LLC before Judge Richard D Bennett. (Court Reporter: Mary Zajac) (hsg, Deputy Clerk) |
Filing 7 [FILED IN ERROR] Local Rule 103.3 Disclosure Statement by Fibrwrap Construction Services, Inc. (Riley, Eileen) Modified on 1/17/2013 (mps, Deputy Clerk). |
Filing 6 [FILED IN ERROR] Local Rule 103.3 Disclosure Statement by Fibrwrap Construction Services USA, Inc. (Riley, Eileen) Modified on 1/17/2013 (mps, Deputy Clerk). |
Filing 5 [FILED IN ERROR] Local Rule 103.3 Disclosure Statement by Fyfe Co., LLC. (Riley, Eileen) Modified on 1/17/2013 (mps, Deputy Clerk). |
Filing 4 Summons Issued 21 days as to Jason Alexander, Mark Geraghty, Shaun Loeding, Anna Pridmore, Structural Group, Inc. (mps, Deputy Clerk) |
Filing 3 MOTION to Expedite Discovery by Fibrwrap Construction Services USA, Inc., Fibrwrap Construction Services, Inc., Fyfe Co., LLC Responses due by 2/4/2013 (Attachments: #1 Memorandum, #2 Text of Proposed Order)(mps, Deputy Clerk) |
Filing 2 MOTION for Temporary Restraining Order, MOTION for Preliminary Injunction by Fibrwrap Construction Services USA, Inc., Fibrwrap Construction Services, Inc., Fyfe Co., LLC Responses due by 2/4/2013 (Attachments: #1 Memorandum, #2 Text of Proposed Order, #3 Exhibit A, #4 Exhibit B)(mps, Deputy Clerk) |
Filing 1 COMPLAINT against Jason Alexander, Mark Geraghty, Shaun Loeding, Anna Pridmore, Structural Group, Inc. ( Filing fee $ 350 receipt number 14637064385.), filed by Fibrwrap Construction Services USA, Inc., Fyfe Co., LLC, Fibrwrap Construction Services, Inc. (Attachments: #1 Civil Cover Sheet, #2 Exhibits, #3 Summons)(mps, Deputy Clerk) |
Access additional case information on PACER
Use the links below to access additional information about this case on the US Court's PACER system. A subscription to PACER is required.
Access this case on the Maryland District Court's Electronic Court Filings (ECF) System
- Search for Party Aliases
- Associated Cases
- Attorneys
- Case File Location
- Case Summary
- Docket Report
- History/Documents
- Parties
- Related Transactions
- Check Status