Ferguson Enterprises, LLC v. Wolfe Construction Company, Inc. et al
2:2020cv00439 |
July 8, 2021 |
US District Court for the Southern District of West Virginia |
Charleston Office |
Contract: Other |
28 U.S.C. ยง 1332 Diversity-Other Contract |
Available Case Documents
The following documents for this case are available for you to view or download:
Document Text |
---|
Filing 16 MEMORANDUM OPINION AND ORDER The 13 Motion for Summary Judgment is granted as to the joint and several liability of Wolfe Construction and Josh Wolfe for $76,367.12, reasonable attorneys' fees, the costs of bringing this action, and pre a nd post-judgment interest; counsel for Ferguson is directed to provide an affidavit and any other supporting materials documenting attorneys' fees and the costs of bringing this action, together with a calculation of pre-judgment interest by 7/2 2/2021; Wolfe Construction and Josh Wolfe may respond to Ferguson's filing by 7/29/2021; the pretrial conference is continued. Signed by Senior Judge John T. Copenhaver, Jr. on 7/8/2021. (cc: counsel of record; any unrepresented parties) (kew) |
Use the links below to access additional information about this case on the US Court's PACER system. A subscription to PACER is required.
- Search for Party Aliases
- Associated Cases
- Attorneys
- Case File Location
- Case Summary
- Docket Report
- History/Documents
- Parties
- Related Transactions
- Check Status
Search for this case: Ferguson Enterprises, LLC v. Wolfe Construction Company, Inc. et al | |
---|---|
Search News | [ Google News | Marketwatch | Wall Street Journal | Financial Times | New York Times ] |
Search Web | [ Unicourt | Legal Web | Google | Bing | Yahoo | Ask ] |
Disclaimer: Justia Dockets & Filings provides public litigation records from the federal appellate and district courts. These filings and docket sheets should not be considered findings of fact or liability, nor do they necessarily reflect the view of Justia.